2x3-42-1/4" Board
1x3-29-1/4" Trim Board
Step 5
Layout Plates for Back Wall
Position (2) two 2x4-10' boards
together and indicate with 'X' marks,
where the wall studs will be located.
10' - 0" Wall Plate
24"
24"
11-1/4"
X
X
Step 4
Install Front Gable Overhang and Front Loft Doors
1.
Apply 47" long 2x3 boards to the front gable. These boards have a blue marking on one end.
Install this end at the top. Install flush with the top of the gable frame. Use 10d sinkers
2.
Install a 42-1/4" long 2x3 at the sides of the gable, flush with the frame. Board will extend
below siding.
3.
Install 29-1/4" long 1x3 trim boards on each side of the loft door opening. Install a 43" long
trim board across the top.
4.
Install loft doors using 4" hinges and 1-1/4" long hinge screws. The screws have a square head.
The bit is packed with the screws. Install barrel bolts to the inside top of the doors to secure
doors when closed. When door is closed mark where bolt will hit 2x4 gable frame. You will
need to drill a 1/4" hole into the underside of the 2x4.
Install Ends With Blue
Mark At Ridge
2x3-47" Board
4" Hinge
1x3-43" Trim Board