Air
Space
Truss
Shingles
1.
Install a 1x4-6' white pine fascia board against the rear gable trim. Install the fascia so the
bottom edge of the roof sheathing will rest on the edge of the 1x4. See Detail 'E'. Use a straight
edge to align the 1x4 board with the top of the trusses. Use 6d galv. nails.
2.
Install another 6' fascia board. Do not install the last fascia board. This will be applied after
the front overhang is installed.
3.
Repeat on opposite side wall.
Step 14 Install Fascia on Side Walls
Step 15A Install Roof Sheathing
2.
Plumb each truss and gables.
3.
Refer to sheathing layout at the top of the next
page. Install roof sheathing starting at the front
gables lower corner. The roof sheathing should
extend 6-1/4" beyond the 2x3s. Continue to back
wall. Use 6d common spaced 8" apart. The top
row of roof sheathing will be about 1" below
the ridge to allow for optional ventilation.
42-3/8" Long 2x3
Front Gable
1x4 Fascia
2x4 Truss
Roof Sheathing
2x4 Tie Plate
2x4 Soffit Block
Detail 'E'
1x4 -6' Fascia Board
Straight Edge
Nail Fascia to
2x4 Block
6-1/4"
1.
Install (4) four 42-3/8" long 2x3 boards on the
front gable flush with the top of the gable frame.
Use 10d sinkers