Filling the circuit

FILLING THE CIRCUIT

Perform the following steps before starting up the system.

1 - FLUSHING AND SEAL TESTING THE SYSTEM

If copper piping has been used and joints have been hot 

brazed, flush out the system to remove any brazing resi-

dues. Seal test the system after you have flushed it out.

 

b

Fill the solar collector with glycol/water mix immedi-

ately after flushing it out, because flushing water may 

remain trapped in the circuit (with a consequent risk 

of freezing).

2 - PREMIXING WATER + GLYCOL

Glycol anti-freeze is supplied separately in standard vol-

umes and must be premixed with water in a suitable con-

tainer before being used to fill the system. For example, 

a mix of 40% glycol and 60% water provides anti-freeze 

protection down to a temperature of -21°C.

 

b

The propylene glycol supplied is specially formulat-

ed for solar collector applications and remains fully 

efficient throughout the -32 to +180°C temperature 

range. It is also non-toxic, biodegradable and bio-

compatible.

 

b

Do NOT part fill the circuit with pure glycol then add 

water later.

3 - FILLING

 

b

Only fill and bleed the solar circuit at ambient temper-
ature, with the collectors shielded from the sun’s rays.

1  Open the non-return valve (A)

2  Open the air vent at the highest point in the system (see 

figure alongside) and keep it open throughout the filling 

operation

3  Open the vent valve (7)

4  Pump the heat transfer fluid around the circuit with an 

external filling pump until all air bubbles have been 

eliminated. Close the manual bleed valve

5  Temporarily raise the pressure in the system to 4 bar

6  Start up the system for about 20 minutes

7  Bleed the circuit again from step 2 until all the air has 

been removed

8  Set the circuit pressure according to the table on the 

next page in order to ensure a minimum pressure of 1.5 

bar at the height of the collector field

9  Close the non-return valve (A) and any open vent valves 

to prevent the heat transfer fluid from evaporating.

 

b

Make sure that you have bled all the air out of the sys-

tem, using the water control system vent too.

Heat transfer fluid filling pump (accessory). A manual 

bleed valve is not required if this pump is used.

Anti-freeze

Temperature

Density

50%

-32 °C

1.045 kg/dm

3

40%

-21 °C

1.037 kg/dm

3

30%

-13 °C

1.029 kg/dm

3

°C

M

A

R

M

7

Anti-freeze mix

Water control system

Heat

transfer fluid

filling pump

Solar collector

Manual

bleed valve

(accessory)

Heat exchanger

of solar

Summary of Contents for SCF-20N

Page 1: ...SOLAR COLLECTOR SCF 20N INSTALLATION MANUAL SOLAR ...

Page 2: ...imals caused by improper installation adjustment maintenance or use Range MODEL CODE SCF 20N 20050326 SCF 20N pack of 2 20050328 SCF 20N pack of 7 20050329 RANGE Contents CONTENTS The following symbols are used in this manual b b CAUTION Identifies actions that require caution and adequate preparation a a STOP Identifies actions that you MUST NOT do This manual Code Rev comprises pages System layo...

Page 3: ...ax glycol concentration Heat transfer fluid water propylene glycol Data plate Serial number plate CODICE 20038360 FABBRICATO IN ITALIA DESCRIZIONE CP20TSA S N COLLETTORE SOLARE PIANO DIMENSIONI 1856X1087X90 mm SUPERFICIE LORDA 2 02 m2 TEMPERATURA DI STAGNAZIONE 198 C SUPERFICIE DI APERTURA 1 81 m2 CONTENUTO LIQUIDO 1 5 l SUPERFICIE ASSORBITORE 1 77 m2 PESO A VUOTO 30 kg LIQUIDO TERMOVETTORE ACQUA ...

Page 4: ... 03 0 04 0 05 0 06 0 07 0 08 Tm m2 K W Optical efficien cy of absorber ηο Thermal dispersion factor of absorber a1 W m2 K a2 W m2 K2 0 764 4 33 0 0069 Tested according to EN 12975 referred to a 33 3 wa ter glycol mix flow rate of 75 l h and irradiation G 800W m2 Tm Coll _inlet _temp Coll _outlet_temp 2 T m Tm T_ambient G WIND AND SNOW LOADS ON COLLECTORS Installation height above ground Wind speed...

Page 5: ...ass compression stop ends The connection with the heat transfer circuit that goes toward the heat exchanger must be the one near the sensor pocket of the last collector of the line The connection with the circuit that comes back from the heat exchanger must be at the bottom of the first collector of the line see the picture above It is also possible to connect more then one line of solar collector...

Page 6: ...6 12 Water control system 5 7 15 16 17 17 18 b b If copper pipes are used joints must be hot brazed b b We recommend the use of stainless steel pipes spe cially made for solar collectors for the outlet return and probe pipes The probe cable should be of the shielded type b b Do not use plastic or multistrate pipes Operating temperature can exceed 180 C b b Pipe lagging must be able to resist high ...

Page 7: ... direct sunlight Failure to comply with these precautions could lead to irreparable damage to the product A B Handling HANDLING Once you have removed the outer packaging proceed as follows to unpack and handle the solar collector Remove the PVC wrapping to free the solar collector from the pallet Tilt the solar collector slightly and grip it at the four points shown A to lift it Use a hoist or oth...

Page 8: ...lation must be protected against damage by the weather and birds and animals Angle of collectors General Solar collectors are designed to be installed at angles of between 15 minimum and 75 maximum Make sure that the bleed and vent valves of the collectors remain open while the collectors are being installed Take care to protect all fittings connections bleed and vent valves against dirt and dust ...

Page 9: ...solar circuit at ambient temper ature with the collectors shielded from the sun s rays 1 Open the non return valve A 2 Open the air vent at the highest point in the system see figure alongside and keep it open throughout the filling operation 3 Open the vent valve 7 4 Pump the heat transfer fluid around the circuit with an external filling pump until all air bubbles have been eliminated Close the ...

Page 10: ...very two years MAINTENANCE Collector circuit Cold circuit pressure ____bar see table above Collector circuit seal test Safety valve check Anti freeze checked to ___ C pH of heat transfer fluid ____ Collector circuit bled Flow rate of 30 l h per m2 checked Non return valve functioning Solar collectors Visual check of collectors Collectors cleaned if necessary Visual check of collector fixing points...

Page 11: ...11 ...

Page 12: ...LC Italy Customer Service 199 13 31 31 www berettaclima it The manufacturer strives to continuously improve all products Appearance dimensions technical specifications standard equipment and accessories are therefore liable to modification without notice ...

Reviews: