COMMISSIONING AND MAINTENANCE

11

16  DEVICE CLEANING AND 

MAINTENANCE

Service the system at least once a year and carry out 

the inspections specified in the relevant manual.

The following operations must be exclusively performed by 

Technical Assistance Centre.

16 1 Checking the seals

After commissioning, check hydraulic fitting sealing. Make 

sure there is no leakage close to electric components to 

avoid short-circuits.

16 2 External cleaning

If dust accumulates on the insulation, clean it with a dry 

cloth.

Do not use abrasive products, petrol or triethylene.

17  INTERVENTIONS ON THE 

HYDRAULIC SYSTEM

17 1 Draining the system

-  Connect a rubber hose to taps (A) and (B)

-  Connect the opposite end to a vessel

-  Open system drain taps and allow full drainage

-  Close system drain taps and remove the rubber hose

-  The exhausted heat transfer fluid must be disposed 

of according to the prevailing regulations, pursuant 

to the instructions provided in the safety data sheet 

supplied with the glycol.

17 2 Disassembling the circulator

Remove the circulator when system has cooled down.

Before removing circulator (C):

-  Cut power off to the solar station and to the connect-

ed integration system, by setting the system's main 

switch and the device's main switch to OFF

-  Disconnect circulator power by removing connectors 

(D) and (E)

-  Move away any wiring and electric devices below to 

protect them against any leakage of heat transfer fluid

-  Close the valve (VR) by turning the handle 90° clock-

wise

-  Open taps (A) and (B) and drain the solar circuit

-  Loosen ring nuts (H1) and (H2) and remove circulator 

(C).

R

RB

VR

A

B

C

H2

H1

E

D

Reverse the above steps to fit the new pump.

Fill the solar circuit as described in paragraph "System fill-

ing cock".

18  RECYCLING AND DISPOSAL

The device is primarily composed of:

Material

Component

metal materials

tubes, circulator

EPP (polypropylene foam)

insulation

electrical and electronic 

components

cable and wiring, circulator

At the end of the device's useful life, these components 

must be separated and disposed of according to current 

regulations in the country of installation.

Summary of Contents for 20116162

Page 1: ...Installation Manual 1 2 3 4 5 0 6 Solar Solar station CONNECT SOLAR R 7 5m Installation Manual EN...

Page 2: ...by a qualified heating engineer b This instruction manual is an integral part of the prod uct It must be kept safe and must ALWAYS accom pany the product even if it is sold to another owner or transfe...

Page 3: ...sed a Do not dispose of packaging material into the envi ronment or leave it within the reach of children since it can become a potential hazard Dispose of packag ing material in compliance with appli...

Page 4: ...ing 7 TECHNICAL SPECIFICATIONS DESCRIPTION Return solar station Maximum working pressure 6 bar Maximum operating temper ature 110 C Dimensions LxHxP 264x362x215 mm Net weight with insulation 3 8 kg Po...

Page 5: ...ll safety and control devices and to permit easy maintenance 9 1 Recommended minimum distances Recommended distances for assembly and maintenance are 300 mm on each side including expansion tank Put t...

Page 6: ...can be used seal fittings with high temperature sealant 180 C suitable for solar applications 12 PUMP CONTROLLER The circulator is produced with maximum hydraulic head configuration of 7 5 meter USER...

Page 7: ...indicates the circulator performance or internal control possibility LEDs no 2 and 3 indicate different control mode possibility and LEDs no 4 and 5 indicate the curve type setting 1 2 3 or 4 These LE...

Page 8: ...rs as shown in the figure PWM CONNEC TOR POWER SUP PLY To control the circulator in on off mode the PWM cable is not required To control the circulator in modulating mode by using a solar regulator ve...

Page 9: ...iL 1 V Input signal current IiH 10 mA Input Duty cycle PWM 0 100 14 SYSTEM FLUSHING Before filling the system with mixture of water and glycol it is necessary to flush the pipes of the solar system to...

Page 10: ...l and water PC PC Heat transfer fluid filling pump To fill the system proceed as follows Verify the flow meter C is completely open Connect the filling pump PC as shown Turn handle on valve VR clockwi...

Page 11: ...the safety data sheet supplied with the glycol 17 2 Disassembling the circulator b Remove the circulator when system has cooled down Before removing circulator C Cut power off to the solar station and...

Page 12: ...23 A 23900 Lecco LC www berettaboilers com The manufacturer strives to continuously improve all products Appearance dimensions technical specifications standard equipment and accessories are therefore...

Reviews: