Installing a Power Disconnect Switch
⚠
WARNING
A Power Disconnect Switch is
not
provided with this
equipment.
A Power Disconnect Switch is a National Electrical Code
(NEC) requirement. They are designed to interrupt main
electrical power in the event of an electrical circuit fault,
emergency situation, or when equipment is undergoing
service or maintenance.
Make sure to install a Power Disconnect Switch that is
properly rated for the incoming power source.
Your Power Disconnect Switch must be readily
accessible and installed so that it is in easy reach of the
operator or in their line of sight. The Power Disconnect
Switch must be clearly marked to indicate its purpose.
The figure to the right shows a toggle-style Power
Disconnect Switch located between the Lift’s power
source and its Power Unit. A quick flip of the switch
immediately cuts power to the Lift.
In the case of the GP-7, the location directly above the
Power Unit is being used by the Lowering Handle, so
your Electrician may want to move the Power
Disconnect Switch location up a little.
⚠
DANGER
Installing a Thermal Disconnect Switch
must
be performed by a licensed,
certified Electrician.
Have the Electrician select a
UL-listed
Power
Disconnect Switch.
Installing a Thermal Disconnect Switch
⚠
WARNING
A GP-7 Series Lift motor has no thermal overload protection.
Have an Electrician connect a motor Thermal Disconnect Switch or overload device that will make sure
the equipment shuts down in the event of an overload or an overheated motor.
⚠
DANGER
Installing a Thermal Disconnect Switch
must
be performed by a licensed, certified
Electrician. Do not perform
any
maintenance or installation on the Lift without first
making sure that main electrical power has been disconnected from the Lift and
cannot
be re-energized until all procedures are complete.
High running amps that exceed the motor’s full load amps (FLA) rating may result in permanent
damage to the motor.
BendPak strongly recommends you
not
exceed the rated duty cycle of the GP-7 Series Lift motor.
Summary of Contents for GP-7
Page 7: ...GrandPrix Two Post Lifts 7 P N 5900209 Rev D3 Feb 2020 Specifications ...
Page 14: ...GrandPrix Two Post Lifts 14 P N 5900209 Rev D3 Feb 2020 Clearances ...
Page 64: ...GrandPrix Two Post Lifts 64 P N 5900209 Rev D3 Feb 2020 Wiring and Hydraulic Schematic ...
Page 65: ...GrandPrix Two Post Lifts 65 P N 5900209 Rev D3 Feb 2020 Parts Diagrams ...
Page 66: ...GrandPrix Two Post Lifts 66 P N 5900209 Rev D3 Feb 2020 ...
Page 67: ...GrandPrix Two Post Lifts 67 P N 5900209 Rev D3 Feb 2020 ...
Page 68: ...GrandPrix Two Post Lifts 68 P N 5900209 Rev D3 Feb 2020 ...
Page 69: ...GrandPrix Two Post Lifts 69 P N 5900209 Rev D3 Feb 2020 ...
Page 70: ...GrandPrix Two Post Lifts 70 P N 5900209 Rev D3 Feb 2020 ...
Page 71: ...GrandPrix Two Post Lifts 71 P N 5900209 Rev D3 Feb 2020 ...
Page 72: ...GrandPrix Two Post Lifts 72 P N 5900209 Rev D3 Feb 2020 ...
Page 73: ...GrandPrix Two Post Lifts 73 P N 5900209 Rev D3 Feb 2020 ...
Page 74: ...GrandPrix Two Post Lifts 74 P N 5900209 Rev D3 Feb 2020 ...
Page 75: ...GrandPrix Two Post Lifts 75 P N 5900209 Rev D3 Feb 2020 ...
Page 76: ...GrandPrix Two Post Lifts 76 P N 5900209 Rev D3 Feb 2020 ...
Page 77: ...GrandPrix Two Post Lifts 77 P N 5900209 Rev D3 Feb 2020 ...
Page 78: ...GrandPrix Two Post Lifts 78 P N 5900209 Rev D3 Feb 2020 Labels ...
Page 79: ...GrandPrix Two Post Lifts 79 P N 5900209 Rev D3 Feb 2020 ...
Page 80: ...GrandPrix Two Post Lifts 80 P N 5900209 Rev D3 Feb 2020 ...
Page 81: ...GrandPrix Two Post Lifts 81 P N 5900209 Rev D3 Feb 2020 ...
Page 82: ...GrandPrix Two Post Lifts 82 P N 5900209 Rev D3 Feb 2020 Maintenance Log ...
Page 83: ...GrandPrix Two Post Lifts 83 P N 5900209 Rev D3 Feb 2020 Maintenance Log ...