8. Commissioning
8.1 Commissioning tasks
For commissioning to be carried out, the following prerequisites must be fulfilled and the preparatory tasks must have
been completed.
Prerequisites
Tools
Material
Protective equipment
• none
• none
•
None
Preparation of installation
1.
Assembly finished including subsequent leakage test
Figure
Description
Automatic discharge
Mechanically open
1.
Set the knurled screw on the float
drain from
>>Mechanically open<<
anti-clockwise (left-hand thread) to
>>Automatic discharge<<
Figure
Description
1
3
2
2.
Open the shut-off valve
[1]
on the inlet
side
slowly
3.
Open the shut-off valve
[2]
on the outlet
side
slowly
4.
Close the shut-off valve
[3]
of the bypass
pipe
Installation and operation manual
CLEARPOINT
®
3
eco
coalescing filter
29 | 56