6.4.4. Alignment of pump-motor unit AS

The pump-motor units positioned on a baseplate and 

with a flexible coupling are aligned before leaving the 

factory.

The pump and motor assembly can lose alignment 

during shipping. Final alignment must be accomplished 

in the field.

  After installation is completed with tightening 

of anchor bolts and connection of pipes, 

alignment of the coupling must be double-

checked before starting the pump. 

If necessary, the unit must be re-aligned.

Remove the coupling guard and with a dial indicator 

or thickness gauge, make sure the distance (3-4 mm) 

between the halfcouplings is the same along the entire 

periphery. 

With a dial indicator or straight edge, check the alignment 

(coaxiality) of the external part of the halfcouplings. 

Control procedure must be performed at 4 diametrically 

opposed, equidistant points on the periphery.

  

After alignment procedure, before starting 

the pump attach the coupling guard (safety 

protection against accidental contact).

6.5. Electrical connection

OFF

  Electrical connection must be carried out only by 

a qualified electrician in accordance with local 

regulations.

Follow all safety standards.

The unit must be properly earthed (grounded).

Connect the earthing (grounding) conductor to the 

terminal with the   marking. 

Compare the frequency and mains voltage with the 

name-plate data and connect the supply conductors 

to the terminals in accordance with the appropriate 

diagram inside the terminal box cover.

  ATTENTION: never allow washers or other 

metal parts to fall into the internal cable 

opening  between  the  terminal  box  and 

stator. If this occurs, dismantle the motor to 

recover the object which has fallen inside.

If the terminal box is provided with an inlet gland, use 

a flexible power supply cord of the H07 RN-Ftype with 

section of cable  not less than 11 TAB IEC 60335-1.

If the terminal box is provided with an inlet bushing, 

connect the power supply cord through a conduit.

For use in swimming pools (not when persons are in 

the pool), garden ponds and similar places, a residual 

current device with IΔN not exceeding 30 mA must be 

installed in the supply circuit.

Install a device for disconnection from the mains 

(switch) with a contact separation of at least 3 mm in 

all poles.

With a three-phase motor install an overload protection 

device with curve D appropriate for the rated current of 

the pump.

Single-phase  AM, are supplied with a capacitor 

connected to the terminals and (for 220-240 V - 50 Hz) 

with an incorporated thermal protector.

7. STARTUP AND OPERATION
7.1.  Preliminary checks before start-up of the

pump

Do not start-up the device in case of damaged parts.

7.2. First starting

OFF

ATTENTION: never run the pump dry. Start the pump 

after filling it completely with liquid.

When the pump is located above the water level 

(suction lift operation) or with a positive suction head 

which is too low (less than 1 m) to open the non-return 

valve, fill the pump through the priming hole (par. 12.3 

fig. 2).

When the liquid level on the suction side is above 

the pump (inflow under positive  suction head), fill the 

pump by opening the suction gate valve slowly and 

completely, keeping the delivery gate valve open to 

release the air.

Before starting, check that the shaft turns by hand. For 

this purpose use the screwdriver notch on the shaft end 

on the ventilation side.

When starting, with a three-phase motor, check that 

the direction of rotation is as shown by the arrows on 

the lantern bracket: clockwise when viewing the motor 

from the fan end. 

Otherwise, disconnect electrical power and reverse the 

connections of two phases.

7.3. Self-priming

(Capability to clear the air in the suction pipe when 

starting with the pump located above the water level 

and when the suction pipe cannot be filled manually, as 

in the case of a missing foot valve).

The  A, AS pumps reprime themselves without the 

necessity of mounting a foot valve up to a depth of  7 m 

(6 m for A 40-110).

Conditions for self-priming:

- pump casing filled with water up to suction port level

before starting (capacity 2 litres for A 40-110, 3 litres

for A 50-125 and 5.5 litres for A 65-150, 8 litres for 

80-170);

-  allow 0,5 m minimum of straight vertical pipe above

the discharge  port;

- suction and discharge valves completely opened;

-  suction pipe with the connections perfectly airtight and 

properly immersed in the water to be lifted;

- mechanical seal perfectly airtight (not damaged).

The pump series A 40 and A 80 are equipped with an air 

release plug  (14.04).

To get a complete filling of the pumpcasing, remove the

plug and make the filling until water will comes out from

this hole.

Close properly the plug before starting the pump.

For the self-priming times see the data sheet.

Summary of Contents for A Series

Page 1: ...OPERATING INSTRUCTIONS Self priming centrifugal pumps with open impeller A AS ...

Page 2: ......

Page 3: ...electrical protection to be installed chapter 6 5 1 1 Symbols To improve the understanding of the manual below are indicated the symbols used with the related meaning Information and warnings that must be observed otherwise there is a risk that the machine could damage or compromise personnel safety The failure to observe electrical information and warnings could damage the machine or compromise p...

Page 4: ...nder conditions other than those indicated in these instructions Improper use of the product reduces the safety and the efficiency of the device Bedu shall not be responsible for failure or accident due to improper use Do not use in ponds tanks or swimming pools or where people may enter or come into contact with the water 2 3 Marking The following picture is a copy of the name plate see Pic 1 tha...

Page 5: ...cts Avoid to impact onto the package materials that could damage the pump If the weight exceeds 25 Kg the package must be handled by two person at the same time 6 INSTALLATION 6 1 Dimensions For the dimensions of the device see technical catalogue 6 2 Ambient requirements and installation site dimensions The customer has to prepare the installation site in order to guarantee the right installation...

Page 6: ...t least 3 mm in all poles With a three phase motor install an overload protection device with curve D appropriate for the rated current of the pump Single phase AM are supplied with a capacitor connected to the terminals and for 220 240 V 50 Hz with an incorporated thermal protector 7 STARTUP AND OPERATION 7 1 Preliminary checks before start up of the pump Do not start up the device in case of dam...

Page 7: ...re not described in this manual must be made only by special personnel authorized by Bedu Pompen BV For further technical information regarding the use or the maintenance of the device contact Bedu Pompen BV 8 1 Routine maintenance OFF Before every maintenance operations disconnect the power supply and make sure that the device could not accidentally operate Never introduce fingers in the inspecti...

Page 8: ...cessary replace it See point 2a also 4 Insufficient flow 4a Pipes and accessories with diameter too small causing excessive loss of head 4b Presence of deposits or solid bodies in the internal passages of the rotor 4c Rotor deteriorated 4d Worn rotor and pump case 4e Excessive viscosity of the liquid pumped if other than water 4f Incorrect direction of rotation 4g Suction head excessive in relatio...

Page 9: ...中文 A AS Rev14 indd 安装使用手册 页码 61 64 12 3 Installation examples Hs 0 5 m 3 93 021 2 3 93 021 2 3 93 021 2 Fig 1 Supports and clamps for pipelines 管路的支撑和固定 Fig 2 Filling 灌泵 Fig 3 Draining ...

Page 10: ...0 00 90 04 82 00 76 04 76 20 81 00 78 00 73 00 76 54 98 08 14 20 36 00 14 24 14 74 14 75 88 04 88 00 82 08 76 06 76 16 28 20 98 04 98 00 70 20 32 00 28 00 28 04 14 64 14 60 14 62 14 12 14 13 14 72 14 73 14 70 46 00 32 30 32 32 32 33 14 04 14 04 1 14 00 76 00 1 94 14 64 14 62 14 72 14 73 14 74 32 00 70 18 14 70 14 75 A 65 150 70 00 A 65 150 ...

Page 11: ...4 72 14 74 64 20 68 00 66 16 66 12 68 04 14 60 14 64 14 00 14 04 28 00 28 20 32 00 60 08 60 04 62 04 66 08 66 04 66 00 14 70 14 75 14 12 36 00 14 24 62 00 46 00 62 08 60 00 64 00 14 20 63 00 28 04 68 08 14 62 28 04 28 20 14 12 36 00 14 24 46 00 62 00 63 00 64 00 66 00 68 00 68 16 4 93 146 2 4 93 146 1 AS 50 125 AS 65 150 Alignment of coupling Ευθυγράμμιση ñÂÌÚ Ó Í ÒÓ ËÌÂÌËfl 4 93 125 2 calibro gag...

Page 12: ...netic compatibility Standards EN ISO 12100 2010 EN IEC 60204 1 2006 EN 809 A1 C1 Additional information No further details Declaration We hereby declare under our sole responsibility that the product s mentioned above to which this declaration relates complies with the above mentioned standards and Directives BEDU Pompen BV Poort van Midden Gelderland Rood 10 6666 LT Heteren Tel 31 0 88 4802 900 F...

Page 13: ......

Page 14: ...orking from our own workplace or at your location A fast and appropriate solution for all your issues Wide range of liquid pumps Repair maintenance and revision made for your process BEDU POMPEN B V Poort van Midden Gelderland Rood 10 6666 LT HETEREN Nederland Telefoon 31 0 88 4802 900 E mail info bedu eu WWW BEDU EU BEDU BELGIUM B V B A Industriepark West 75 9100 SINT NIKLAAS België Telefoon 32 0...

Reviews: