3
B. Equipment storage and installation requirements.
The equipment should be stored or installed in a shady, normal
temperature, ventilated and dry place.
C. SPECIFICATIONS OF CONCRETE
(See Fig. 5)
Specifications of concrete must be adhered to the specification as following.
Failure to do so may result in lift and/or vehicle falling.
1. Concrete must be thickness 7-7/8’’ mm minimum and without reinforcing steel
bars
,
and must be dried completely before the installation.
2. Concrete must be in good condition and must be of test strength 3,000psi
minimum.
3. Floors must be level and no cracks.
D. AIR SUPPLY
Air pressure requirement: 0.5Mpa~0.8Mpa, Air line size
Φ
8 *
Φ
6
and
Φ
6 *
Φ4
.
E. POWER SUPPLY
The electrical source must be 2.0HP minimum. The source cable size must be
2.5mm² and in good condition of contacting with floor.
Fig. 4
≥
7-
7/
8”
Concrete Intensity must be 3000PSI minimum
Summary of Contents for 30-4140A
Page 1: ...FOUR POST LIFT 30 4140A 30 4140AE 30 4140A 30 4140AE...
Page 11: ...9 D Install Cross Beams See Fig 15 Fig 16 Fig 16 2 Hole towards inside 1 3 3 Fig 15...
Page 25: ...23 IV EXPLODED VIEW Model 30 4140S 30 4140SE 1 2 3 8 18 44 203 32 12 54 55 56 57 45 Fig 38 4...
Page 31: ...29 4 3 POWER UNIT EXPLODED VIEW 071102 Fig 42 220V 60Hz Single Phase...