7219840.02 (1-03/16)
32
USER Section
(en)
1. COMMISSIONING THE BOILER
To light the boiler correctly, proceed as follows:
•
Open the gas tap (yellow, normally positioned under the boiler);
•
Check that the hydraulic pressure in the system is correct (section 8);
•
Power the boiler;
•
The boiler leaves the factory with the CH and DHW circuits disabled. Before enabling these circuits, perform the system
VENTING
procedure as described in section 15 SPECIAL FUNCTIONS "
Venting function (312)
". Then enable the CH and
DHW circuits using the
EASY MENU
(
) button as described in section 3. These operations must only be performed
by qualified technicians.
The boiler
control panel
can be installed on the wall to manage the temperature of the room to heat.
During initial ignition, the burner may not ignite (causing the boiler to shut down) until any air in the gas pipes is vented. To
re-ignite the boiler, see section OPERATING MODES.
CONTROL PANEL
Key to SYMBOLS
Burner lit
(Power %: 1<70% - 2>70%)
Operating mode: comfort ambient temperature
Operating mode: reduced ambient temperature
(only if installed indoors)
Operating mode in heating:
1 = zone 1 – 2 = zone 2 – 3 = zone 3
Operating mode: DHW enabled
Operating mode: AUTOMATIC
Operating mode: MANUAL
Ambient temperature (°C)
Connection to SOLAR plant
External temperature (°C)
Fault
Off: heating and DHW disabled
(only boiler anti-freeze protection is active)
Fault preventing the burner from lighting
Flue cleaner function enabled
Technical Service Centre call-in
Holiday programme function enabled
Boiler/system water pressure low
Data transmission
(only if the WIRELESS device is connected)
Set unit of measurement (SI/US)
1.1 BASIC CONTROL PANEL SETTINGS
INITIAL IGNITION CONFIGURATION PROCEDURE
When igniting the boiler for the first time, perform the following procedure (the text is written in
ENGLISH
until the user is requested
to set his/her language as illustrated in sequence A-B-C of the figure indicated below):
•
B
for 5 seconds;
•
the display shows a percentage value from 1 to 100. Data synchronisation takes a few minutes to complete;
• set the language, date and time.
C
B
A
Summary of Contents for NUVOLA PLATINUM +
Page 106: ...7219840 02 1 03 16 106 S E C T I O N A ...
Page 111: ...111 S E C T I O N D 7219840 02 1 03 16 25 mm ...
Page 114: ...7219840 02 1 03 16 114 ...