11
ENGLISH
GB
8.3.
Gas connection (service technician)
A gas connection must be performed in
compliance with the applicable regulations.
Before connecting the appliance, check the
technical data, type of gas, working pressure and
flow rate which are provided on the rating plate.
The installation is performed by connecting the
connection pipe of the appliance with a pipe of the
gas distribution network. A shut-off valve must be
installed on the connection to shut the gas supply
off if necessary.
If there are significant pressure differences in the
gas supply installation, it is recommended to
install a pressure regulator.
After the installation, check the gas connection for
tightness.
When looking for gas leaks do
not use the open flame!
8.4.
Extraction of fumes
Installation of the type “A” devices does not
envisage connection to the fume exhaust system,
but to the appropriate extraction hood which
discharges the fumes to outside.
Installation under the extraction hood (A)
Place the device under the extraction hood (
1
)
and attach a pipe to the device outlet of the size
as shown on the figures.
The end of the fume extraction pipe should be
located at least 1.8m above the floor.
Gas supply of the device should
be
directly
subjected
to
forced
extraction system: blocking of the fan
must shut the gas supply off.
The fan must switch on automa-
tically when the gas valve is open.
ID 08