ANCHOR SYSTEM INSTALLATION
INSTRUCTIONS
(Day 1) continued:
1. Mix and pour concrete into hole. Follow instructions
on concrete bag. Stop about 18" below court level.
2. Insert four reinforcement bars into concrete
8" apart creating a square in center on hole.
3. Finish pouring concrete up to court level.
4. Push anchor system into concrete and agitate to work
out voids in concrete. Immediately use a level to level
and square anchor plate to playing surface. Clean
off any concrete that may be on exposed threads.
Note: The bottom four nuts will be forever
embedded in concrete.
Let concrete stand for a MINIMUM of 7 days.
Figure 1 Detail
Anchor plate must be square
to the court so the backboard
will line up properly.
3.