10 | Baker Hughes
© 2021 Baker Hughes Company. All rights reserved.
8.3.2. Start-up
•
Before switching on or after doing any work on the device, always tighten the cover (C) with a
seal (J) in good condition and put back the safety screw (V).
•
Check that the cable gland is certified for the intended use and that the electrical data are
suitable for the operating zone.
Note:
Before start-up, proceed, if required, with instrument calibration as per §9 and/or ensure that all
the safety instructions in the preceding paragraphs have been strictly followed.
9. Calibration of the 7700E Positioner
•
Comply with current national and local regulations for electrical installation work.
•
Must be installed and put into service in conformance with national and local regulations applicable
for explosive atmospheres.
•
Before carrying out any work on the device, power off the instrument or make sure that the local
conditions in the potentially explosive atmosphere permit the safe opening of the cover.
•
Connect the wires to the instrument
’s terminals taking care of complying with polarities and
maximum voltage allowed
•
Before switching on or after doing any work on the device, always tighten the cover (C) with a
seal (J) in good condition and put back the safety screw (V).
The positioner assembled on valve is factory-calibrated, but if it is necessary to remake the calibration on
the site, it will be carried out by the customer according to the following general principles
•
Make the pneumatic and electrical connections, see
and
•
The adjustment of the starting pressure is made by screw (K116). Calibrate the electrical signal
corresponding to the closing of the valve (4 or 20 mA). Turn the take-up screw (K116) until the piston
rod just begins to move (the plug leaves the contact with the seat ring).
•
Tighten the locknut (K117).
•
Strictly follow safety instructions under
Note: the I/P 4000 module does not require any adjustment.