INSTALLATION
UNPACKING AND INSPECTION
2 - 2
I-E96-406A
®
UNPACKING AND INSPECTION
These are steps to follow for general handling:
1. Examine the unit to make sure that no damage has
occurred in transit.
2. Notify the nearest Bailey Controls sales office of any dam-
age.
3. File a claim for any damage with the shipping company
that handled the shipment.
4. Use the original packing material or container to store the
unit.
5. Store the unit in a place with clean air; free of extremes of
temperature and humidity.
SETUP/PHYSICAL INSTALLATION
This section explains how to install the NTAM01 unit. The
required procedures are installing the termination unit into the
field termination panel and connecting the communication
cables.
Termination Unit Installation
The NTAM01 unit mounts on a standard NFTP01 Field Termi-
nation Panel. Figure
shows how to secure the termination
unit to the NFTP01 panel.
To install the termination unit:
1. Make sure power is off to the cabinet.
2. Insert the termination unit tabs into the slots in the outside
edge of the termination panel.
3. Mount the termination unit to the field termination panel
with two, number 10, ¾-inch screws. Do not overtighten the
screws. See Figure
.
Cable Installation
The NTAM01 unit has four cable connectors, P1 through P4,
that connect to round, shielded cables. An NKTU01 and
NKTU11 cable connects P2 to the primary IMAMM03 module.
A second NKTU01 and NKTU11 cable connects P3 to the
redundant IMAMM03 module, if it is used. Up to four NTAI02
units can be interconnected to P1 through NKAI01 and NKAI11
cables.