56
22-1/2"
(57 cm)
24"
(61 cm)
24"
(61 cm)
24"
(61 cm)
24"
(61 cm)
22-1/2"
(57 cm)
ROOF PANELS
3/8"
(9,5 mm)
3/8"
(9,5 mm)
12"
(30,5 cm)
6"
(15 cm)
PARTS REQUIRED:
x2
7/16 x 47-7/8 x 48"
(1,1 x 122 x 122 cm)
x108
2" (5 cm)
3/4" GAUGE
BLOCK
x1
7/16 x 48 x 96"
(1,1 x 122 x 244 cm)
Keep spacing between the center of the rafters
at the lower edge of the panel and secure
using (1) 2" nail into each rafter
(Fig. E)
.
Move to the top of the panel and keep spacing
between the center of the rafters. Secure
using (1) 2" nail into each rafter
(Fig. E)
.
Nail the roof panel using 2" nails 6" apart on
edges and 12" apart inside panel.
Install
47-7/8 x 48"
roof panel flush to
first panel, flush at peak and with the 3/8"
measurement on trim
(Fig. F, G)
.
4
Move to the opposite side of the roof and
repeat this process installing a 48 x 96”
and 47-7/8 x 48” panel.
Note the panels edges are offset from the
first panels installed.
Make sure panels are flush at the peak
(Fig H)
and there is a 3/8” measurement
at the gable trims
(Fig. J)
.
Nail the roof panel using 2” nails 6” apart
on edges and 12” apart inside panel.
5
Gable
Trim
NOTE:
Measurements from inside of panels
Fig. F
Fig. H
Fig. J
Fig. G
Fig. E
2" Nails
Flush
at peak
Flush
at peak
Flush
96"
48"