4

4

OPERATION

To operate the Oxor II, you simply . . .

Set its POWER switch to ON,

Wait for the instrument to warm up (approx. 1 minute),

Span the display (if necessary),

Take a gas sample.

Detailed operating procedures are presented below:

4.1

Power ON/OFF

Turn on the instrument by sliding its POWER
switch to ON. Observe that when power is first
applied, all numerical LCD segments and the deci-
mal point are tested for 5-15 seconds; after which, the LCD shows the
detected O

2

 level. (A minus sign may appear during power up as the

sensor stabilizes.) Turn off the instrument by sliding the POWER
switch to OFF.

4.2

Adjusting the Instrument

After being turned on and warmed up for at least 1 minute, the
instrument should indicate 20.9% in fresh air. If the instrument needs
to be zadjusted, proceed as follows:

1. Ensure that the instrument is sampling fresh air that is free of any

oxygen displacing gases.

2. Using a 1/8" flat-blade screwdriver, turn the

ADJUST potentiometer until the LCD shows
20.9%. 

An instrument can be considered prop-

erly adjusted with a display bounce of up to ±0.2%.

4.3

Backlight ON/OFF

The LCD can be read in low-light areas by setting the front panel
LIGHT switch to ON. The backlight stays on until turned off, or until
the POWER switch is set to OFF.

Summary of Contents for OXOR II 19-7037

Page 1: ...n Analyzer Part No 19 7037 19 7044 Rev 6 October 1999 Bacharach Inc 621 Hunt Valley Circle New Kensington PA 15068 PH 724 334 5000 FAX 724 334 5001 Web www bacharach inc com E mail help bacharach inc...

Page 2: ...icalsensors arewarrantedforaperiod of six months THE FOREGOING WARRANTIES ARE EXCLUSIVE AND ARE GIVEN AND ACCEPTED IN LIEU OF I ANY AND ALL OTHER WARRANTIES EXPRESS OR IMPLIED INCLUDING WITHOUT LIMITA...

Page 3: ...ory or training assistance should be obtained before use Assistance is available by calling your nearest Bacharach Service Center 1 INTRODUCTION TheOxor IIisacommercial gradepor tableinstrumentdesigne...

Page 4: ...observ ingproperbatterypolarity installfour C size batteriesintotheinstrument sbatterycompart ment Recommended battery types Duracell Alkaline or equivalent After the batteries are installed replace t...

Page 5: ...trument s electronic circuitry The instrument will operate once batteries are properly installed and the PTC thermistor is allowed to cool 3 2 Probe Installation Install the probe by sliding the end o...

Page 6: ...abilizes Turn off the instrument by sliding the POWER switch to OFF 4 2 Adjusting the Instrument After being turned on and warmed up for at least 1 minute the instrument should indicate 20 9 in fresh...

Page 7: ...the metal clip at the bottom of the instrument s case you can hang the instrument by its strap on nearby objects such as nails sheet metal or valve handles 4 5 Using the Probe Thebasicprobe ortheoptio...

Page 8: ...eds to be calibrated at regular intervals to ascertain that it still meets its accuracy specification A regular calibration schedule should be established Detailed calibration maintenance procedures a...

Page 9: ...lds Court Unit 3 Markham Ontario L3R 9W7 Canada Phone 905 470 8985 Fax 905 470 8963 E mail bachcan idirect com M xico Bacharach de M xico Playa Regatas No 473 Tercer Piso Col Militar Marte Delegaci n...

Page 10: ...Notes 8...

Reviews: