background image

In the event of extended lifts or where hazards exist, the lifting devices should be used in conjunction with safety

slings placed under the unit.

Anchoring

The unit must be properly anchored in place.
Refer to the suggested support details on the certified drawing for locations of the mounting holes. Anchor bolts

must be provided by others.
Holes suitable for 19 mm bolts are provided in the bottom flange of the cooler support structure for bolting the unit

to the support beams.

Leveling

The unit must be level for proper operation and ease of piping.
Support beams must also be level as shims should not be used between pan and support beams to level the unit.

Connecting Pipework

All piping external to BAC cooling equipment must be supported separately.
In case the equipment is installed on vibration rails or springs, the piping must contain compensators to eliminate

vibrations carried through the external pipework.

Purge Requirements

The installer of BAC closed circuit cooling towers must ensure a proper air purging of the system prior to operation.
Entrained air can restrict the capacity of the cooler, resulting in higher process temperatures.

Freeze Protection

These products must be protected against damage and/or reduced effectiveness due to possible freeze-up by

mechanical and operational methods. Please refer to the BAC Product & Application Handbook or contact your

local BAC Balticare representative for recommended protection alternatives.

Safety Precautions

All electrical, mechanical and rotating machinery constitutes a potential hazard, particularly for those not familiar

with its design, construction and operation. Accordingly, adequate safeguards (including use of protective

enclosures where necessary) should be taken with this equipment both to safeguard the public (including minors)

from injury and to prevent damage to the equipment, its associated system and the premises.
If there is doubt about safe and proper rigging, installation, operation or maintenance procedures, contact the

equipment manufacturer or his representative for advice.
When working on operating equipment, be aware that some parts may have an elevated temperature. Any

operations on elevated level have to be executed with extra care to prevent accidents.

W W W . B A L T I M O R E A I R C O I L . C O . Z A

5

1 General Information

1 General Information

Summary of Contents for SP2B series

Page 1: ...SP Adiabatic Cooler RIGGING AND INSTALLATION INSTRUCTIONS RSPv07EN SA...

Page 2: ...enance and Monitoring Programme Checks and Adjustments Start Up Every Month Every 3 Months Every 6 Months Every Start of Adiabatic Season Spring Adiabatic Pre Cooler water flow X X X Tighten Electrica...

Page 3: ...alking Surfaces 6 Modifications by others 7 Warranty 7 2 Rigging 8 General Notes 8 Rigging Method 9 3 Section Assembly 12 Installed Adiabatic Pre Cooler 12 Installation of screw on Flanges 13 4 Option...

Page 4: ...hould be checked thoroughly to ensure all required items have been received and are free of any shipping damage prior to signing the bill of lading The following parts should be inspected Exterior pan...

Page 5: ...ir can restrict the capacity of the cooler resulting in higher process temperatures Freeze Protection These products must be protected against damage and or reduced effectiveness due to possible freez...

Page 6: ...speed For more information consult your local BAC Balticare representative ELECTRICAL SAFETY Each fan associated with this equipment should be installed with a lockable disconnect switch located withi...

Page 7: ...from manufactured defects in materials and workmanship for a period of 12 months from the date of shipment In the event of any such defect BAC will repair or provide a replacement For more details pl...

Page 8: ...th safety slings placed under the unit 4 For each unit only one lift is required Lifting ears are foreseen on each unit 5 Attach the lifting devices to the unit as per rigging methods below Do not use...

Page 9: ...g a spreader beam should be used and the angles shown in the diagrams below must be observed End View End view Side View All 2 fan units 3 fan units A models Fan diameter 910 mm W W W B A L T I M O R...

Page 10: ...3 fan units B models Fan diameter 1250 mm 4 fan units A models Fan diameter 910mm All 5 fan units W W W B A L T I M O R E A I R C O I L C O Z A 10...

Page 11: ...All 6 fan units W W W B A L T I M O R E A I R C O I L C O Z A 11 2 Rigging 2 Rigging...

Page 12: ...ler Sections and number of drains per model Model Number Size of Fans Number of Adiabatic Pre Cooling Sections Unit Number of Bottom Drains Unit SP2B 2 fans 1250 mm 2 2 SP3B 3 fans 1250 mm 4 4 SP4B 4...

Page 13: ...ation of screw on Flanges Care must be taken when installing screw on flanges on the fluid connections of the unit to make sure no forces are transferred from the flange to the copper header of the un...

Page 14: ...W W W B A L T I M O R E A I R C O I L C O Z A OPTIONAL ACCESSORIES ASSEMBLY All optional Accessories are factory installed 14 SP 4 4 Optional Accessories Assembly 4 Optional Accessories Assembly...

Page 15: ...ctioning of mechanical components or operational problems e g unwanted ice formation If this occurs a thorough inspection of the entire unit followed by immediate corrective action is needed If requir...

Page 16: ...ipment is standard provided with a door interlocked main power switch Q0 which is factory fitted Connect electrical power to the power switch through a 3 pole cable with ground of adequate cross secti...

Page 17: ...sitions Permitted Positions for mounting VFD sensor Not Permitted positions for mounting VFD sensor W W W B A L T I M O R E A I R C O I L C O Z A 17 5 Inspection Prior to Start up 5 Inspection Prior t...

Page 18: ...Reset C01 Power Failure Relay H0 Indicating Lamp QBO Power Invertor By pass Switch optional F0 Main Fuses with optional Inverter By pass Switch Legend for Electrical Panel with Variable Frequency Dri...

Page 19: ...sensor regulating the fan rpm accordingly 6 The unit will now operate according to the load demand When the inverter reaches the maximum speed the controller will activate the adiabatic system by ener...

Page 20: ...ended Code of Practice to keep your Cooling System efficient and safe Eurovent Cecomaf 2002 30p Guide des Bonnes Pratiques Legionella et Tours A ror frig rantes Minist res de l Emploi et de la Solidar...

Page 21: ...W W W B A L T I M O R E A I R C O I L C O Z A...

Page 22: ...W W W B A L T I M O R E A I R C O I L C O Z A...

Page 23: ...W W W B A L T I M O R E A I R C O I L C O Z A...

Page 24: ...W W W B A L T I M O R E A I R C O I L C O Z A...

Page 25: ...W W W B A L T I M O R E A I R C O I L C O Z A...

Page 26: ...STORAGE EVAPORATIVE CONDENSERS HYBRID PRODUCTS PARTS SERVICES www BaltimoreAircoil co za info BaltimoreAircoil co za Please refer to our website for local contact details PO Box 32088 7808 Ottery Cape...

Reviews: