AZBAT48100B Product Manual
Page 10 of 17
All Rights Reserved.
Revision 1.00
February 2021
Azoteq
PowerSense
®
Series
a. Red and black cables as depicted in Figure 5.
b. Please ensure the power cables are properly torqued to minimum 10N.m for the M8
terminal.
5. Connect the cables to the inverter via the DC fuse and breaker.
a. Please ensure the polarity of the connection between the inverter and the batteries
are correct.
6. Connect the RS485 cables between the batteries when using multiple batteries.
a. As depicted by the yellow connections in Figure 5.
7. Connect the CANBUS cable between the master battery and the inverter.
a. As depicted by the blue connection in Figure 5.
8. Setup the DIP switches on the batteries for parallel use.
a. Please refer to section 5.4 for more detail on the DIP switch settings.
Figure 5: AZBAT48100B installed inside a battery cabinet with 3 batteries connected in parallel.