
9-16
Chapter 9 Maintenance and Inspection
9-3
Inspection
Insulation Resistance Test and Withstand Voltage Test
As a rule, do not test the insulation resistance or withstand voltage.
Lightning arrestors are incorporated into the probe and junction box. When these tests are
conducted, the built-in lightning arrestors may be damaged.
If testing must be done, follow the steps below.
(1) Disconnect all of the external wiring completely from each device.
(2) The test locations are shown below. The tests can be conducted with the + and -
terminals of the core wires of the hollow cable, connector terminals, and SUPPLY
terminals shorted.
y
Probe
For the probe with the cable in the hollow pipe : between the core wires (+, -) of the
hollow cable and the shielded wires
For the probe alone
: between the connector terminals
(+, -) and the probe case
y
Junction box
Between the SUPPLY terminals (+, -) and the ground terminal of the junction box
(3) The applied voltages and judgment criteria are shown in the table below. To prevent
the meter from being damaged, do not apply a voltage exceeding the value shown
below.
Insulation resistance test
Withstand voltage test
Probe and junction box
At 25 V DC
20 MΩ or more
50 V AC for 1 minute
Set current 2 mA
Summary of Contents for ALTJ 9000 Series
Page 1: ...CM2 JTL100 2001 ALTJ 9000 Immersion Type Liquid Level Transmitter User s Manual...
Page 14: ...1 6...
Page 18: ...2 4...
Page 28: ...6 2...
Page 34: ...7 6...
Page 38: ...8 4...
Page 58: ...9 20...
Page 60: ...10 2...
Page 64: ......
Page 65: ......
Page 66: ......
Page 68: ......