NA-814 Hardware Installation Guide
Installation Procedures
18
PS, The above mention pictures for CPU deployment instruction was
adopted by Intel internet web
Put the copper heat sink on the upper of CPU. The fin of heat sink should
be vertical run from I/O shield. To use the four screws to clamp the heat
sink.
2.4.3 Installing a memory module (DIMM)
The
main board
can supports two 184-pin DDR socket for a maximum
total memory up to 2GB
None-ECC unbuffer Memory
.
CPU FSB
DDR Type
DDR Frequency
800MHz PC3200/PC2700/PC2100 400/333*/266MHz
533MHz PC2700/PC2100
333/266MHz
*Because limited of chipset, when using FSB800Mhz CPU, PC2700
DDR (333Mhz) only support 320Mhz.
Attention:
¾
When you handle electrostatic discharge-sensitive
(ESDs), take
precautions to avoid damage from static electricity.
2.4.4 Installing a DMA33/66/100 hard drive
To accommodate the fast transfer rate of Ultra DMA33/66/100, a cable
(with 40 pin connectors on both ends) is necessary when installing Ultra
DMA33/66/100 drives. The
NA-814
, on this aspect, can support IDE hard
drive and DOM (Disk on Module) deployment. It is through the IDE
Connector (CN18)
Put the HDD into a tray. Plug the IDE round cable for hard drive and main
board both side. Then put the tray to the right-back site of the system
Summary of Contents for NA-814
Page 1: ...NA 814 Hardware Installation Guide For service person only...
Page 11: ...NA 814 Hardware Installation Guide Introduction 5 1 4 Dimensions...
Page 16: ...NA 814 Hardware Installation Guide Installation Procedures 10 2 2 Board Placement...
Page 42: ...SBC8A814 Hardware Installation Guide Award BIOS Utility 36...
Page 47: ...SBC8A814 Hardware Installation Guide Award BIOS Utility 41...
Page 56: ...SBC8A814 Hardware Installation Guide Award BIOS Utility 50...