Installation and Setup
Power and Water Connections
The power and Water connections are located on the right side of the unit. The table below identifies the
power, pressure adjustment, and water connections to the Pico unit.
Fittings
The feed water, inlet and outlet tubing is inserted and secured through the fittings defined in Table 3. All
fittings are plugged for shipping purposes. A plug must be inserted into any fitting that is not used.
To remove the plug, hold the plug in one hand and while pushing the fitting collar, pull out the plug.
Figure 4. Fitting collar (left).
Table 3. Power and water connections for the Pico unit.
Power Inlet from external 24 VDC power supply unit
Feed water inlet. Low pressure, less than 1 bar [15 psi]
Feed water inlet, High pressure, greater than 1 bar [15 psi]
Pump pressure adjustment. Factory set to 5.5 to 6 bar [79 to 87 psi]
Reservoir overflow connected to drain
RO concentrate outlet connected to drain.
Summary of Contents for Pico PICO10T2
Page 1: ...Pico Water Purification System Operation Manual OP 000100 Revision D August 2018...
Page 22: ...Pico Water Purification System Operation Manual Avidity Science LLC 16 Installation and Setup...
Page 34: ...Pico Water Purification System Operation Manual Avidity Science LLC 28 Maintenance...
Page 38: ......
Page 40: ...Pico Water Purification System Operation Manual Avidity Science LLC 34 Replacement Parts...