2.2 Electrical Installation

3. Operation

•  AtmosAir FC400 series systems require approximately 4.0 watts. The FC-400 series can be wired directly to 

single-phase blower circuits.

•  Follow proper electrical procedures, guidelines, and codes for providing power to the systems, including 

requirements for conduit, sufficient ampacity, phase balancing, etc. Electrical installation should be performed 
by a qualified electrician.

•  Field-install a power plug outlet or junction box within 6 feet (1.8m) of the unit(s).

•  Each FC-400 series unit is typically shipped with a 8-foot (2.4m) power cord with a field install pair of wire hot/

neutral connector on one end and a quick disconnect plug on the other end. FC-400FM has a polarized quick 
disconnect on the unit. Each unit is shipped with 2 wiring options per country-specific requirements:

1. 

2 conductor, field wire connection (No Ground)

2. 

NEMA 5-15 2-prong plug adapter

Once the system is properly installed and 

ALL PERSONNEL ARE CLEAR

 of the high voltage tubes, the system can 

be turned on:

1. 

Ensure the ionization power knob is turned all the to the appropriate quadrant. From low to high clockwise.

2. 

Plug the power cord into the plug receptacle on the FC-400 ionization system. (The FC-400 Series units are 
shipped with a quick disconnect spade terminals. The male and female terminals are specifically arranged 
so that the polarity can only be connected the correct way. Eliminating the risk of damaging the unit by 
accidentally reversing the polarity.

Caution!

A non-functioning LED light may improperly indicate that the system is not functioning. Be sure to disconnect 

from the main power before performing maintenance or troubleshooting the system.

provided to locate the cut-out hole, then cut out with a 2.5” (6.35cm) Hole Saw and mark the locations of the 
mounting holes for the FC-400FM. Mark the drill holes for the self tapping screws to mount the FC-400 FM to 
the Duct Wall.

6. 

Affix the unit securely in the duct using self-tapping screws . Do not over-tighten, this may strip the screw-hole. 
The unit is self-sealing to the duct so no further sealing is needed.

7. 

Units should be installed to allow easy access for maintenance. Install units so that the power adjustment knob, 
fuse and status light are easily accessible, variable and visible.

2.1 Mechanical Installation Continued...

Summary of Contents for FC-400FM Series

Page 1: ...door air to its pure natural state where no pollution or contaminants exist while reducing energy use and emmisions in the process Our Mission Breathing is Believing sm Installation Operation Maintena...

Page 2: ...allation is complete and personnel are aware of the imminent operation Carefully read this instruction booklet before beginning the installation Follow each installation or repair step exactly as show...

Page 3: ...9 001 USA Table of Contents 0 Important Warnings 0 2 Table of Contents 1 Product Overview 1 2 Product Diagrams 2 Installation 2 1 Mechanical Installation 2 2 Electrical Installation 3 Operation 4 Main...

Page 4: ...verity of the pollution and odors The AtmosAir FC 400 series equipment is designed for minimal maintenance The FC 400 series has two components that require inspection and maintenance 1 AtmosAir FC 40...

Page 5: ...ape to ensure the unit seals properly Make a 2 5 6 35cm Diameter hole in the duct that the FC 400FM tube will fit into See Fig 1 2c Use template AtmosAir FC 400 series equipment can be mounted on a du...

Page 6: ...e tubes the system can be turned on 1 Ensure the ionization power knob is turned all the to the appropriate quadrant From low to high clockwise 2 Plug the power cord into the plug receptacle on the FC...

Page 7: ...n hear the buzz of the tube then the unit is functioning properly If not proceed to the troubleshooting section for repair Maintain a physical distance between all personnel and the tubes while system...

Page 8: ...AN FLAT TO TUBE contact with the tube as shown below The next step is to determine the cause of the failure or blown fuse Typically failures are caused by arcing between the inner and outer electrodes...

Page 9: ...ration solutions AtmosAir equipment uses non thermal plasma technologies to generate bi polar Ionization that attacks and breaks down odors and contaminants More Solutions Commercial solutions start w...