Besam ICU/CCU - Equal or Unequal Panel  

20
© Copyright 2007 Besam Entrance Solutions.  May not be reprinted or reproduced without permission.

Mechanical Installation

Full Breakout Sidelite Installation Procedure

Surface and Recessed Track Applications - Equal/Unequal Panel

Note:

  Remove any glass stops or packing material from the sidelite before installation. 

1.  Install and level any thresholds (surface or recessed) before installing any of the 

door panels.

2.  Check that jamb mounted bottom pivot is installed and tight.
3.  If the pivot base does not rest fully on the floor, support the pivot base with shims.
4.  Loosen the setscrew in the top pivot.
5.  Place the bearing washer on the pivot base. Check that bottom and top pivots 

are  tight  in  the  door.  Set  the  sidelite  on  the  pivot  and  tilt  it  into  place.  There 

should be no more than 1/8" between the bottom of the header and the top of 

the  sidelite. To  adjust,  remove  the  sidelite,  raise  or  lower  the  bottom  pivot  by 

loosening the set screw at the side of the floor portion of the pivot and turn the 

shaft clockwise to lower the sidelite and counter clockwise to raise the sidelite; 

then retighten the set screw. With the sidelite on the bottom pivot, carefully push 

down the top spring-loaded pivot pin and line it up with its receiving hole in the 

header until the shaft pops into place (See Fig. 9, pg. 21).

6.  Check all clearances and make adjustments to the break out ball catch.
7.  When all sidelite panels are installed, tighten top pivot security set screw to pre-

vent depressing pivot pin.

8.  Install glass using proper glass blocking techniques to ensure proper operation 

of door package. See page 27.

Trackless Applications - Unequal Panel ONLY

Note:

  Remove any glass stop or packing material from the sidelite before installation. 

1.  Install  pivot  plate  flush  to  jamb  on  non-cover  side.  See  Fig.  5  &  6,  Pg.  21  

(Sec A-A).

2.  Install  DHD  foot  assembly  to  the  bottom  of  the  sidelite.  See  Fig.  5  &  7,  Pg.  21 

(Sec. B-B).

3.  Loosen the setscrew in the top pivot.
4.  Place the bearing washer on the pivot base. Check that bottom and top pivots 

are  tight  in  the  door.  Set  the  sidelite  on  the  pivot  and  tilt  it  into  place.  There 

should be no more than 1/8" between the bottom of the header and the top of 

the  sidelite. To  adjust,  remove  the  sidelite,  raise  or  lower  the  bottom  pivot  by 

loosening the set screw at the side of the floor portion of the pivot and turn the 

shaft clockwise to lower the sidelite and counter clockwise to raise the sidelite; 

then retighten the set screw. With the sidelite on the bottom pivot, carefully push 

down the top spring-loaded pivot pin and line it up with its receiving hole in the 

header until the shaft pops into place (See Fig. 9, pg. 21).

5.  Check all clearances and make adjustments to the break out ball catch.
6.  When all sidelite panels are installed, tighten top pivot security set screw to pre-

vent depressing pivot pin.

7.  Install glass using proper glass blocking techniques to ensure proper operation 

of door package. See page 27.

Summary of Contents for besam US23-0696-01

Page 1: ...Solutions May not be reprinted or reproduced without permission Besam ICU CCU Equal or Unequal Panel Installation Adjustment and Troubleshooting Manual Complies with NFPA 101 Life Safety Code for Man...

Page 2: ...d equipment damage Adjust doors for proper operation in accordance with manufacturer s instruction and adherence to NFPA 101 Life Safety Code and or AHJ Authority Having Jurisdiction In the following...

Page 3: ...on Examples 12 Installation Requirements 13 Opening Closing and Locking of the cover 14 Site Inspection 15 Mechanical Installation 16 26 Checking Marking out Fastening 16 Leveling Header and Jambs 16...

Page 4: ...ambs The header supports the sliding doors and sidelites Models Equal panel door packages can be bi parting 4 panel or single slide 2 panel left or right handed and sidelites may be installed fixed or...

Page 5: ...Issue 7 23 2007 Besam ICU CCU Equal or Unequal Panel Copyright 2007 Besam Entrance Solutions May not be reprinted or reproduced without permission Part Identification Options...

Page 6: ...Issue 7 23 2007 Besam ICU CCU Equal or Unequal Panel Copyright 2007 Besam Entrance Solutions May not be reprinted or reproduced without permission Part Identification Options...

Page 7: ...ue 7 23 2007 Besam ICU CCU Equal or Unequal Panel Copyright 2007 Besam Entrance Solutions May not be reprinted or reproduced without permission Part Identification Options Sidelite FSL Unequal Panel O...

Page 8: ...7 23 2007 Besam ICU CCU Equal or Unequal Panel Copyright 2007 Besam Entrance Solutions May not be reprinted or reproduced without permission Part Identification Options Active Leaf FSL Unequal Panel...

Page 9: ...Issue 7 23 2007 Besam ICU CCU Equal or Unequal Panel Copyright 2007 Besam Entrance Solutions May not be reprinted or reproduced without permission Part Identification Options Sidelite FBO...

Page 10: ...Issue 7 23 2007 Besam ICU CCU Equal or Unequal Panel 10 Copyright 2007 Besam Entrance Solutions May not be reprinted or reproduced without permission Part Identification Options Active Leaf FBO...

Page 11: ...Issue 7 23 2007 11 Besam ICU CCU Equal or Unequal Panel Copyright 2007 Besam Entrance Solutions May not be reprinted or reproduced without permission Space Required...

Page 12: ...Issue 7 23 2007 Besam ICU CCU Equal or Unequal Panel 12 Copyright 2007 Besam Entrance Solutions May not be reprinted or reproduced without permission Installation Examples...

Page 13: ...2 min 2 50 mm from the underside Besam minimum recommended requirements Building Codes may give dif ferent specifications Thinner wall profiles must be reinforced with rivnuts Tools required Carpente...

Page 14: ...d cover just above the weather stripping Rotate the wrench 90o toward the cover Feel for lip on the lock and slide about a 1 2 away from the jamb Gently pull up on the cover to ensure the lock has com...

Page 15: ...or in the direction of break out should ideally be 90 or greater measuring from the highest point of the floor see below See Fig 1 The rough opening width should be 1 2 wider than the overall frame wi...

Page 16: ...floor see Fig 1 page 15 if there is a slight rise in the floor at any point then the bottom of the jambs should be set level with the highest point of the floor with the header leveled across the ope...

Page 17: ...line from jamb to jamb on the side where the track is being installed 3 Using the measurements provided see Fig 3 below lay the track in place While stand ing on the track and keeping it in line with...

Page 18: ...glass stops or packing material from the sidelite before installation 1 Place sidelite on G track Line up the 2 connecting posts located approximately 6 from each end of the top horizontal with the 2...

Page 19: ...e wheel brackets on top of the door onto the track inside the header 4 Install the anti risers by sliding the door past the anti riser block and lin ing up the carrier and block Insert anti riser bolt...

Page 20: ...djustments to the break out ball catch 7 When all sidelite panels are installed tighten top pivot security set screw to pre vent depressing pivot pin 8 Install glass using proper glass blocking techni...

Page 21: ...07 21 Besam ICU CCU Equal or Unequal Panel Copyright 2007 Besam Entrance Solutions May not be reprinted or reproduced without permission Mechanical Installation Fig 5 Fig 6 Fig 7 Fig 8 Trackless Unequ...

Page 22: ...sam ICU CCU Equal or Unequal Panel 22 Copyright 2007 Besam Entrance Solutions May not be reprinted or reproduced without permission Mechanical Installation Fig 9 FBO Sidelite Installation Trackless Su...

Page 23: ...s into the track 3 Install the anti risers by sliding the door past the anti riser block and lin ing up the carrier and block Insert anti riser bolt and secure See Fig 11 Pg 25 4 Adjust the vertical a...

Page 24: ...onto the track inside the header See Fig 14 6 Install the anti risers by sliding the door past the anti riser block and lin ing up the carrier and block Insert anti riser bolt and secure See Fig 11 Pg...

Page 25: ...Issue 7 23 2007 25 Besam ICU CCU Equal or Unequal Panel Copyright 2007 Besam Entrance Solutions May not be reprinted or reproduced without permission Mechanical Installation Fig 11 Fig 12 Anti Riser...

Page 26: ...urer s instruction and adherence to NFPA 101 Life Safety Code and or AHJ Authority Having Jurisdiction Tension is not to exceed 50 lbs breakout force To adjust use a 1 2 wrench on the wrench flats to...

Page 27: ...Issue 7 23 2007 27 Besam ICU CCU Equal or Unequal Panel Copyright 2007 Besam Entrance Solutions May not be reprinted or reproduced without permission Mechanical Installation Glazing and Blocking...

Page 28: ...07 Besam Entrance Solutions May not be reprinted or reproduced without permission Copyright 2007 Besam Entrance Solutions May not be reprinted or reproduced without permission Besam Entrance Solutions...

Reviews: