Ø 1 mm
Ø 6,35 mm
T-part with Inserting
DN50 plug
G1/4” threaded
Pool Chemicals Connection
At this step is necessary to connect the injecting valves of individual
chemicals to the dosing pumps and dosed agents.
Place the injecting valve in the T-joint, blinded with the
DN50 G1/4” threaded
plug #12134.
1.
Cut the PE tube at 90 ° angle to ensure proper fi tting.
•
Use the sharp knife to cut plastic. The cut must be clean and smooth.
2.
Drill the 6 mm hole and the 1 mm hole (air suction) into the CHLORPURE
canister cap. Push the PE tube through the cap. Select the tube distance
so that the tube reaches the canister bottom and can be connected to
the pump as straight as possible. A long tube in the canister would bend
and produce air bubbles.
3.
Put a weight on the tube end and dive it in the canister.
4.
Connect the plastic tube from the pH canister to the pump to the left
connection.
5.
Connect the plastic tube to the pump right connection and the injection
valve.
6.
Hand screw the injection valve in the specifi ed mounting hole (see
diagram).
•
The injection valve is installed in G 1/4” thread.
•
Check throughput of the injection valves and tightness of the entire
system.