background image

Before Y

ou Begin / Site P

reparation

Antes de empezar/Preparación del sitio

 

Avant de commencer/Préparation du terrain

1.

 Before beginning construction, check local building codes

regarding footings, location and other requirements.

Study and understand this owner

’s manual.

2.

 F

ollow all directions and dimensions car

efully

.

3.

 Follow the step sequence carefully for correct results.

4.

 Be sure all the parts fit together properly before

proceeding.

5. IMPORT

A

N

T: 

Remove Owner

’s Manual fr

om main carton

1.

 

Antes de empezar la construcción, verifique los códigos de

construcción locales relativos a cimentación, localización

y otros requisitos.  Escudriñe y entienda este manual del

propietario.

2.

 

Siga todas las instrucciones y dimensiones con cuidado.

3.

 Siga la secuencia de pasos con cuidado para realizar

resultados correctos

.

4. 

Asegure que todas las piezas se junten apropiadamente antes

de continuar

.

5. 

IMPORTANTE:

 Saque el Manual del Propietario de la caja

de cartón principal de su edificio de almacenaje.

6.  LA SEGURIDAD ANTE TODO: 

 Hay que tener cuidado al

manejar las varias piezas de su juego porque algunas tienen

bordes afilados.  Póngase guantes de trabajo, protección

para los ojos y mangas largas cuando ensamble o cuando

dé cualquier mantenimiento a su juego.

7. HERRAMIENTAS BASICAS: 

 Destornillador Phillips núm.

2, alicates, guantes de trabajo, cinta métrica, nivel y azada

o pala.

8. EL SUELO DEBE ESTAR NIVELADO: 

 Asegure que los

marcos del piso estén planos en el suelo. Para preparar la

base de tierra, quite césped y otros escombros. Nivele los

sitios altos con una pala plana y apisone la base.

9. ¡NO PISE LOS CANALES HASTA QUE EL MATERIAL DE

PISO ESTE EN SU LUGAR!

10.

 

Disponga el contenido de la caja de cartón por el número

de la pieza mientras repasa la lista de piezas. Controle para

asegurar que Vd. tenga todas las piezas necesarias de su

juego.

1.

 A

vant de commencer la constr

uction, réviser les normes locales

de sécurité de construction relatives aux empattements, à

l‘emplacement et aux autres exigences.

2.

 Suivre attentivement toutes les directives et les dimensions.

3.

 Suivre attentivement la séquence des étapes pour obtenir les

résultats désirés.

4.

 Avant de poursuivre, s‘assurer que toutes les pièces sont

correctement ajustées.

5. IMPORTANT :

 Retirer le Guide du propriétaire qui se trouve

dans l‘emballage principal de la remise.

6. 

SÉCURITÉ D‘ABORD :

 Manipuler soigneusement les diverses

pièces du prêt-à-monter puisque certaines d‘entre elles ont des

angles coupants. Porter des gants de travail, une protection

oculaire et des manches longues pour assembler le prêt-à-

monter ou pour effectuer des travaux d‘entretien.

7. 

OUTILS ESSENTIELS :

 tournevis Phillips n

o

 2, pinces, gants

de travail, mètre à ruban, niveau, bêche ou pelle.

8. 

ÉGALISER LE TERRAIN :

 S‘assurer que les pièces de la

charpente du plancher reposent à plat sur le sol. Pour préparer

le lit de terre, enlever le gazon et les autres débris. Égaliser les

points plus élevés avec une pelle plate et taper le lit de terre

.

9.

 NE PAS MARCHER SUR LES TRAVERSES AVANT D‘AVOIR

POSÉ LE REVÊTEMENT  DU PLANCHER!

10.

 Déballer les pièces selon leur numéro de pièce tout en

consultant la liste des pièces. S‘assurer que toutes les pièces

nécessaires se trouvent dans l‘emballage.

Assembly

Montage * Ensamblaje * Assemblage

 

or write * 

Oder schreiben Sie an 

*  

o escriba * ou écrire

Arrow Group Industries

 1101 North 4th Street, Breese, Illinois 62230

Include Model Number

, P

art Number and P

art Name

• 

Bitte geben Sie Ihre Modellnummer, Teilenummer und

Teilebezeichnung an.

• Proporcione número del modelo, número de la pieza y

nombre de la pieza.

• Indiquer le numéro de modèle, le numéro de pièce et la

désignation de la pièce.

• Si encuentra que le hacen falta piezas, llame al 1-800-851-1085

 

If you find a part missing call

 

1-800-851-1085

of your storage building.

6. SAFETY FIRST

:

  Car

e must be tak

en when handling various pieces

of your kit since some contain sharp edges.  W

ear work gloves,

eye protection and long sleeves when assembling or performing

any maintenance on your kit.

7. BASIC TOOLS:

  No

. 2 Phillips scr

ewdriver

, pliers, work gloves, tape

measure, level and a spade or shovel.

8. GROUND MUST BE LEVEL:

  Be sure Floor Frames lie flat on ground.

To

 pr
epar

e earth bed, r

emove sod and other debris.

Level the high spots with flat shovel and tamp the bed

down.

9.DO NOT STEP ON CHANNELS UNTIL FLOORING MATERIAL

IS IN PLACE!

10. 

Separate contents of the carton by the part number

while reviewing parts list.  Check to be sure that you

have all the necessary parts for your kit.

Bevor Sie anfangen / Vorbereitung der Baustelle

1.

Vor Baubeginn überprüfen Sie örtliche Bauvorschriften auf Erfordernisse

hinsichtlich Fußflächen, Bauplatz und weitere Erfordernisse. Lesen Sie dieses

Besitzerhandbuch sorgfältig und verstehen Sie es.

2.

Befolgen Sie alle Anweisungen und Abmessungen sorgfältig

.

3.

Zur Erzielung richtiger Ergebnisse halten Sie die Reihenfolge der Schritte

genau ein.

4.

Bevor Sie weitermachen, vergewissern Sie sich, daß alle Teile richtig

zusammenpassen.

5.

WICHTIG:

 Nehmen Sie das Besitzerhandbuch aus dem Hauptkarton Ihres

Lagerschuppens heraus.

6.

SICHERHEIT KOMMT ZUERST:

 Verschiedene Teile Ihres Bausatzes müssen

vorsichtig gehandhabt werden, da sie scharfe Kanten haben. Tragen Sie beim

Zusammenbau oder bei der Durchführung von Wartungsarbeiten an Ihrem

Bausatz Arbeitshandschuhe, Augenschutz und lange Ärmel.

7.

GRUNDWERKZEUGE:

 Nr. 2 Kreuzschlitzschraubenzieher, Zange,

Arbeitshandschuhe, Maßband, Wasserwaage und ein Spaten oder eine

Schaufel.

8.

DER BODEN MUSS EBEN SEIN:

 Vergewissern Sie sich, daß die Bodenrahmen

flach am Boden liegen. Zur Vorbereitung des Erdbetts entfernen Sie die

Grasdecke und anderen Schutt. Ebnen Sie höhere Flächen mit einer flachen

Schaufel ein und stampfen Sie das Bett nieder.

9.

STEIGEN SIE ERST AUF DIE KANÄLE, WENN DAS BODENMATERIAL

PLAZIERT IST!

10.

Sortieren Sie den Kartoninhalt nach der Teilenummer, während Sie die

Teileliste überprüfen. Vergewissern Sie sich, daß Sie alle für Ihren Bausatz

notwendigen Teile haben.

1.

  

Before assembling this kit, the floor

frames pack

ed with the building must

be assembled.

• Vor dem Zusammenbau dieses Bausatzes

müssen die mit dem Gerätehaus mitgelieferten

Bodenrahmen zusammengebaut werden.

• Avant de monter ce kit, les cadres de planchers

fournis avec le bâtiment doivent être montés.

• Antes de armar este kit, se deben ensamblar

los entramados del piso comprimidos con el

edificio.

Summary of Contents for 697.68604-A1

Page 1: ...715830210 Missing Parts Questions on Assembly Call 1 800 851 1085 Do not return to dealer they are not equipped to handle your requests Storage Area 129 Sq Ft 852 Cu Ft 12 0 m2 24 1 m3 BUILDING DIMENSIONS Size rounded off to the nearest foot CAUTION SOME PARTS HAVE SHARP EDGES CARE MUST BE TAKEN WHEN HANDLING THE VARIOUS PIECES TO AVOID A MISHAP FOR SAFETY SAKE PLEASE READ SAFETY INFORMATION PROVI...

Page 2: ...ble by mail order or at your local dealer or you may construct a base and anchoring system of your choice Your assembly instructions provide information on a few methods commonly used to secure and level a storage building Parts and Parts List Check to be sure that you have all the necessary parts for your building All part numbers can be found on the parts All of these numbers before the must agr...

Page 3: ...mwork Whenever possible two or more people should work together to assemble your building One person can position parts or panels while the other is able to handle the fasteners and the tools Tools and Materials These are some basic tools and materials you will need for the construction of your building Decide which method of anchoring and the type of base you wish to use in order to form a comple...

Page 4: ...ntrate your total weight on the roof of the building When using a step ladder make sure that it is fully open and on even ground before climbing on it Keep children and pets away from worksite to avoid distractions and any accidents which may occur Do not attempt to assemble the building if parts are missing because any building left partially assembled may be seriously damaged by light winds Call...

Page 5: ...ricate door track annually with furniture polish or silicone spray Keep doors closed and locked to prevent wind damage Fasteners Use all washers supplied to protect against weather infiltration and to protect the metal from being scratched by screws Regularly check your building for loose screws bolts nuts etc and retighten them as necessary Moisture A plastic sheet vapor barrier placed under the ...

Page 6: ... lag bolt into a concrete slab Full assembly instructions and a 1 4 masonary drill bit are included TOOL HANGING RACK Model No TH100 The perfect tool organizer Twin 25 1 2 64 8 cm steel channels plus five heavy duty snap in hangers and a small tool holder for screwdrivers pliers etc Holders slide along channel for fully adjustable spacing Great for garage basement or the back of any door Fits all ...

Page 7: ...THIS PAGE WAS LEFT BLANK INTENTIONALLY 7 ...

Page 8: ...THIS PAGE WAS LEFT BLANK INTENTIONALLY 8 ...

Page 9: ...easure 16 24 40 6 cm 61 0 cm sections to construct inside frame see diagram Secure plywood to frame using 4 penny galvanized nails Allow 6 7 hours for construction OPTION 3 Concrete Slab The slab should be at least 4 10 2 cm thick It must be level and flat to provide good support for the frame The following are the recommended materials for your base 1 x 4 s 19 mm x 89 mm will be removed once the ...

Page 10: ...on instruction AnchoringintoConcrete 1 For poured concrete slab or footing or patio blocks Use 1 4 x 2 6 mm x 51 mm Lag Screws 2 For Anchor Post of Concrete poured after building is erected Use 1 4 x 6 6 mm x 152 mm Lag Screws ArrowAnchoringKit ModelNo AK4or60298 Recommended for use with any suggested base Contains 4 Anchors with Cable Clamps and installation instruction AnchoringintoWood Post Use...

Page 11: ...4 66183 Roof Trim Cap 2 right 2 left 66045 Handle 2 66646 Washer 521 14 sheets of 40 65109 8 32AcornNut 4 PackedwithScrews 67468 Peak Cap 6 ArrowLogo 65004 8Ax5 16 8mm Screw 446 65923 8 32x3 8 10mm Bolt 240 65900A 10Bx1 2 13mm BlackScrew 8 PackedwithScrews 65103 8 32HexNut 240 Hardware SO11 6228 Track Support 2 66769 Door Slide 4 ...

Page 12: ...0475 RightandLeftDoors 2 15 9369 DoorJamb 2 16 67521 EdgeTrim Clear 2 17 6015 SideRoofTrim 2 18 6403 Door Track Splice 1 19 6797 RidgeCap 6 20 6869 RidgeCap 3 21 6892 RightSideRoofTrim 2 22 6893 LeftSideRoofTrim 2 23 9366 Door Track 2 24 5986 RearWallAngle 2 25 10389 RearWallChannel 2 26 10388 SideWallChannel 4 27 9365 FrontWallChannel 2 28 6085 RoofBeamBracket 4 29 6227 RoofBeamBrace 2 30 10386 R...

Page 13: ...4 4 5 5 7 7 37 37 37 37 37 16 16 28 28 6 6 19 19 20 28 28 29 29 30 30 31 31 3 3 3 3 12 12 12 12 12 12 12 12 26 26 2 2 27 27 35 35 36 10 10 14 14 15 15 11 11 1 1 10 10 18 32 32 32 32 12 12 12 12 25 34 34 34 24 24 34 33 33 23 23 26 25 26 30 30 30 30 13 Assembly by Key No SO13et ...

Page 14: ...s will align when the pieces are positioned with cor rect amount of overlap See the illus trations below for the proper overall lengthofthesideandrearfloorframes Join the frames by inserting four five bolts into each frame set as shown 3 Double check the length of each and set these pieces aside for later use Step 1 SO14hw Parts Needed For Floor Frame Assemblies 8934 Ramp 1 9367 Front Floor Frame ...

Page 15: ... with one bolt in the center hole 4 Make two side wall angles by overlapping the side wall angle pieces as shown Fasten each set together with one bolt thru the sec ond large hole from the end of each part 5 Double check the length of each and set these pieces aside for later use 5986 Rear Wall Angle 2 10389 Rear Wall Channel 2 10388 Side Wall Channel 4 10391 Side Wall Angle 4 STEP 1 STEP 2 10389 ...

Page 16: ...f the pressed together roof beams and join them as shown toformthemainroofbeamassembly Hold the assembly together and fas ten with 14 bolts Build only one Doubled Beam Assembly 3 Fasten the other two pressed together roof beams with eight bolts to make the left and right roof beam assemblies 4 Double check the length of each and set these pieces aside for later use Step 3 SO16hw Parts Needed For R...

Page 17: ...iding doors and reinforces the frontwall Itismadeupofthreepieces 1 Using the door track splice painted join the door track galvanized pieces end to end as shown 2 Insert four screws from the under side only Hint The holes in the top side of the doortrackassemblyareforfastening the gable to the top of the front wall in a later step 3 Position door slides onto the legs from the end of door track ass...

Page 18: ...At the front corners fasten bolts through from the bottom with nuts on top 2 Measure the floor frame diago nally When the diagonal measure ments are equal the floor frame is square NOTE If using a wood platform or concrete slab do not fasten the floor frames to your base at this time You will anchor the building after it is erected STEP 1 10387 RIGHT REAR 8936 Level 10387 RIGHT FRONT 9367 STEP 2 W...

Page 19: ...all Panel 2 9373 Front Wall Panel 2 6020 Corner Panel 4 Step 6 SO19hw Parts Needed For Corners NOTE The remainder of the building assembly requires many hours and more than one person Do not continue beyond this point if you do not have enough time to com plete the assembly today A partially assembled building can be severely damaged by light winds Each screw and bolt in the wall requires a washer...

Page 20: ...asten the rear wall channel across the middle of the rear wall using screws 2 Fasten the side wall channels across the middle of the side panels using screws Fasten overlaps in rear corners with bolts and nuts at two locations See the figure NOTE The wall channels behind the front wall panels will be installed in a later step STEP 1 2 STEP 10388 10389 FRONT 2 STEP 20 4 ...

Page 21: ...l angle across the inside top of the rear wall using screws 2Fastenthesidewallanglesacross the inside top of the side panels us ing screws Side wall angles must overlap rear wall angle in corners 3 Fasten the door track assembly holes on top across the top of the front wall panels using screws See the figure STEP 1 3 STEP 9366 5986 FRONT 2 STEP 10391 LongLeg on Top Opening facing in ShortLeg on Bo...

Page 22: ...he building 2 Fasten the wall panels at the top and bottom with screws 3 Fasten the center of each panel to the wall channel with screws 4 Fasten overlapping ribs as before STEP 1 3 STEP 4 STEP 6515 Bolt and nut does not go thru wall channel at overlap Panels rest on frameasshown 6515 CrimpedRib Underneath 2 STEP DetailShowing Center of Panel Screwed to WallChannel Useboltsandnuts thru wall angle ...

Page 23: ...t this time 2 Fasten a door jamb to the front panel with two bolts nuts and acorn nuts as shown 3 Fasten the center of the door jamb to the front wall panel and the front wall channel with two screws 4Fastenthetopofthe doorjambto the door track with two screws Do the same for the bottom into frame Repeat steps 2 through 4 for the opposite door jamb 23 Acorn Nut Hex Nut 9369 F R O N T Screw Screw T...

Page 24: ...andnutson each side This part of the gable is called the outer gable leg 4 Attach the four roof beam brackets to the outer gable legs us ing two bolts in the two bottom holes of the four holes that align Parts Needed For Gable Assemblies Step 11 SO24et 6108 Large Right Gable 2 6109 Large Left Gable 2 6114 Small Right Gable 2 6115 Small Left Gable 2 6085 Roof Beam Bracket 4 STEP 1 STEP 3 6085 Roof ...

Page 25: ... gable use a bolt and nut at the overlapping rear wall angle 2 Fasten the single roof beam to the outer gable leg as shown using bolts Hint The holes along the length of the beam must be on the top surface RepeatStep1fortheoppositesideof building 3 Join the left and right gables together with a gable brace using a bolt in the second hole from the bottom only Do this step for both front and rear ga...

Page 26: ...Roof Beam Brace 6227 STEP 7 10386RoofBeam Double 4 Fasten the other end of the double roof beam to the gable brace of the rear gable 5 Fasten a roof beam brace to the double roof beam behind the front gable by placing the tab on the end of the brace between the roof beams Align the tab with the second hole and fasten the brace with a bolt and nut 6 Fasten the lower end of the roof beam brace to th...

Page 27: ...p Kit was purchased assemble prior to attaching the roof panels 1 Locate the roof panels and find the right roof panel part number 6188 2 Position a right roof panel at the backrightcornerandfastentothetop roof beam using screws 3 Remove edge trim from the left gable under the roof panel 4 Continue fastening the right roof panel to the gable and lower roof beam using screws bolts and nuts as shown...

Page 28: ... Caps Panels 2 Cut 34 short 3 7 6 cm strips off the small roll of weather stripping tape and put them aside Cover the joint at the peak with weather strip ping tape large roll Unroll the tape andpressitdownovertheopeningat the ridge as you install each roof panel Donotcutthetapeatthistime 4 Install three ridge caps 6797 on the completed roof section using bolts and nuts Do not fasten the ends of t...

Page 29: ...ove the ridge cap to the side and overlap the ribs of the next roof panel 3 Install two roof panels 6538 as before working side to side while fastening down ridge caps NOTE If roof beam holes do not line up with the roof panel holes shift the building from left to right If this does not help your building may not be level Shim the corners until holes line up Parts Needed For Ridge Caps Panels 6538...

Page 30: ...nd right roof panel6188 asyouunrolltheweather stripping tape and press it down Fasten the lower end of the panels to the side wall angles using screws and washers 3 Fasten the roof panel ribs peak caps and ridge caps together using bolts and nuts Reducing Large Gable Bulge Loosen eight bolts and nuts shown Apply pressure with one hand at the peak of the gable and tighten bolt 1 Keeping pressure on...

Page 31: ...nd the bottom flange of the side roof trim at the corner inward enough so the right and left roof trim caps fit onto right and left corners 3 Fasten the roof trim caps to the side trim using a screw 6893 Left Side Roof Trim 2 6892 Right Side Roof Trim 2 6015 Side Roof Trim 2 Parts Needed For RoofTrim Step 18 SO31hw Tuck Flange Inward to Fit Inside of Roof Trim Cap STEP 2 Roof Trim Cap STEP 3 6892 ...

Page 32: ...crew 3 Hold the vertical door brace against the center of the inside sur face of the door and turn the screw to hold the vertical door brace and door handle brace in place Fasten to door above and below center connection using 2 screws 4 Insert a second bolt in the door handle and tighten both bolts 5 Put a horizontal door brace onto the top edge and bottom edge and fasten with 1 bolt in the cente...

Page 33: ... the door slides 3 Fasten the door to the door slides usingtwo 10Bx1 2 13mm screws per door slide NOTE The holes in the door slides allow you to adjust the doors Place the door in the middle holes 4 Repeat steps 1 through 3 for the left door STEP 2 HorizontalDoorBrace STEP 1 Gable STEP 3 10Bx1 2 13 mm Screw DoorSlide Adjustment Holes Adjustment Holes Allow Doors to Meet Evenly AlongTheirLength Rig...

Page 34: ...Anchoring Anchor your building at this time Floor Frame If you have purchased a Floor Frame Kit you need to install it at this time 34 Anchoring and Floor Frame XA34hw ...

Page 35: ...adre pour plancher Kit de entramado de pisos 10192 16 10194 2 10 x 11 Building Qty Part Name Bau 3 05 x 3 35 Edificio de 3 05 x 3 35 Remise 3 05 x 3 35 Menge Cantidad Quantité Teilbezeichung Nombre de la pieza Désignation de la pièce 10192 18 10194 2 Part Name Teilbezeichung Nombre de la pieza Désignation de la pièce Bau 3 05 x 3 96 Edificio de 3 05 x 3 96 Remise 3 05 x 3 96 Qty Menge Cantidad Qua...

Page 36: ...ièces selon leur numéro de pièce tout en consultant la liste des pièces S assurer que toutes les pièces nécessaires se trouvent dans l emballage Assembly Montage Ensamblaje Assemblage or write Oder schreiben Sie an o escriba ou écrire Arrow Group Industries 1101 North 4th Street Breese Illinois 62230 Include Model Number Part Number and Part Name Bitte geben Sie Ihre Modellnummer Teilenummer und T...

Page 37: ...2 Assemble parts that overlap Five 5 Sheets 4 x 8 for 10 x 14 10 x 13 Four 4 Sheets for 10 x 12 10 x 11 Fünf 5 Platten zu 1 22 mx2 44 m für 3 05mx4 27m und 3 05mx3 96m Vier 4 Platten zu 1 22 mx2 44 m für 3 05mx3 66m und 3 05x3 35 Cinco 5 hojas de 4 x 8 1 22 m x 2 44 m para 10 x 14 y 10 x 13 Cuatro 4 hojas de 4 x 8 1 22 m x 2 44 m para 10 x 12 y 10 x 11 Cinq 5 panneaux de 4 x 8 pour 10 x 14 et 10 x...

Page 38: ...eau no 4 56 2 cm x 79 7 cm Sheet 1 48 x 78 3 4 Sheet 4 48 x 76 1 2 Sheet 5 22 1 8 x 78 3 4 Sheet 2 48 x 76 1 2 Platte 2 Hoja núm 2 Panneau no 2 121 9 cm x 194 3 cm 121 9 cm x 191 9 cm ES1014 697 68740 48 x 75 9 16 ES1014 697 68740 22 1 8 x 75 9 16 121 9 cm x 191 9 cm Platte 1 Hoja núm 1 Panneau no 1 121 9 cm x 200 cm Platte 5 Hoja núm 5 Panneau no 5 56 2 cm x 200 cm Sheet 3 48 x 78 3 4 Platte 3 Ho...

Page 39: ...as it appears 1 Avoid nicking or scraping the coating surface inside and out 2 Use all the washers supplied In addition to pro tecting against weather infiltration the washers pro tect the metal from being scraped by the screws 3 Keep roof base perimeter and door tracks free of debris and leaves which may accumulate and retain moisture These can do double damage since they give off acid as they de...