Installation pro-
cedure (Fig.3)
Step
Action
1
carefully examine the installation area, eliminating any danger to the
operator;
2
remove the package only if the cabinet is placed in the opera
-
tion area
3
lift the cabinet safely
4
use suitable scissors to cut the clip tightening straps-A-
5
remove the clips and the frame
6
lower and place the cabinet in the area of use
7
adjust the horizontal position of the cabinet using a spirit level (Fig.8)
8
check that all feet are into contact with the floor
9
level the cabinet both in front and back
Install maximum 3 cabinets within the same power supply and cooling
l i n e
Should you need to move the cabinet, the latter must be levelled again.
Incorrect levelling
What to avoid
DO NOT install the cabinet (Fig.7):
-
in areas at risk of explosion
-
in open air and therefore subjected to atmospheric agents;
-
near heat sources (direct sunlight, heating systems, incandescence
lamps, etc.)
-
in the vicinity of air currents (close to doors, windows, air-conditio
-
ning systems, etc.) that exceed a speed of 0.2 m/s
First cleaning
•
gently remove the protective film, eliminate glue residues with suitable sol
-
vents
•
carry out the first cleaning using neutral products, dry with a soft cloth
DO
NOT use alcohol to clean the methacrylate (Plexiglas) parts
DO
NOT use abrasives or metal sponges
CAUTION
! Discarded packing parts. Injury.
Do
not leave packing parts (nails, wood, staples, etc.) and tools used for the operation (pliers,
scissors, etc.) in the working area.
These objects must be removed with appropriate means and taken to their respective col
-
lection places.
i
For correct disposal, the package consists of:
Wood - Polystyrene - Polythene - PVC - Cardboard.
13. 1 London 3: assemble and adjust the guard
Assembly:
Attach the guard onto the fins of the guard support as in Fig. 10
Adjustment:
Operate on the adjustment screws of the guard support as in Fig. 11
14. Joining the cabinets (Fig.22)
Pitch
Action
1
Disassemble the shoulders (if present).
2
Position the cabinets side by side.