![Argo ECOLIGHT PLUS 12000 UE User And Installation Manual Download Page 40](http://html1.mh-extra.com/html/argo/ecolight-plus-12000-ue/ecolight-plus-12000-ue_user-and-installation-manual_2967509040.webp)
V 11/21
95
Note: the link card is only for reference, plase take into consideration the actual one.
4. Reposition the terminal block cover and tighten the screws.
5. Close the panel.
N.B.:
• All wiring must be connected as shown on the unit's wiring diagram.
All indoor and outdoor unit cables must be connected by a qualified technician.
•
If the power cable is not long enough, contact the supplier for a new one. Do not attempt to
extend it yourself.
• For air conditioners equipped with a plug, the plug must be easily accessible upon completion
of installation.
• For air conditioners without a plug, install a circuit breaker on the line.
The circuit breaker must
be single-pole and the contact gap must be greater than 3mm.
Step eight: bind the pipes
1. Bind together the connecting pipe, the power
cable and the drain pipe with binding tape.
3. Bind them evenly.
4. The liquid pipe and gas pipe must be bound
separately at the end.
2. Reserve a section of the drain pipe and power
cable for installation when binding. When you
have bound up to a certain point, separate the
indoor power cable and then the drain pipe.
N.B.:
The power cable and signal control cable must
not be rolled or coiled.
The
drain pipe must be bound at the bottom.