Decking
Assembly
2
Archatrak Inc.
D E C K I N G
Assembly
3
Use SE pedestals to elevate StreetDeck perimeter.
H
3.2
Elevate remainder of perimeter frame towards opposite
6’ side. Place pedestals every 24” and use level along
perimeter frame to check for necessary pedestal height
adjustments. Typically shorter pedestals are necessary
on the street edge, transitioning to incrementally taller
pedestals toward the sidewalk edge.
3.1
Begin on one of the 6’ sides. Snap off the 4 spacer tabs
on pedestal heads to allow underside of frame to sit
flush on pedestal head. Pedestal heights are adjusted
by holding the screw column firmly and rotating the
pedestal base left or right to raise/lower the pedestal.
StreetDeck perimeter height should be level with
sidewalk height so ramp will sit flush on pavers and
sidewalk.
1
Decide ramp location and install ramp brackets with
protruding end as close to sidewalk as possible.
Shift assembled deck closer to sidewalk if necessary.
1.1
Use two ramp brackets per ramp. Choose ramp
location based on existing holes located on either end
of perimeter beam (see above). Use one hex head bolt
and flange nut to attach each ramp bracket to the
perimeter beam.
Repeat this step if you have more than one ramp.
Do not attach ramp to brackets until pavers are laid.
Sidewalk Edge
M
G
M
2
Square deck frame by measuring distance between
diagonal corners and shifting frame as necessary until both
measurements are equal.
Sidewalk Edge
6’
Sidewalk Edge
Street Edge