APsystems YC500 Quick Design Guide
ii
Step 1.
Verify that the grid voltage matches the
microinverter specifications.
Step 2.
Install the AC branch circuit junction box.
Step 3.
Connect the cables to the AC branch circuit
junction box.
1. Connect the open wire end of the AC branch end splice cable into
the junction box using an appropriate gland or strain relief fitting.
2. Wire the conductors: L1- RED; L2 - BLACK; N -WHITE.
3. Connect the AC branch circuit junction box to the point of utility
interconnection.
Step 4.
Attach the APsystems microinverters to the racking
or the PV module frame.
Figure 1
Figure 2
Figure 3