4 Installation
B40IB006EN-D
17
4 Installation
4.1 Installation Requirements
TIP: When HTK 1200N is ordered together with the
required adapter, the adapter is mounted on the
chamber on delivery.
When HTK 1200N is ordered together with a motor-
ized alignment stage, the adapter is mounted on the
alignment stage.
Operation of HTK 1200N/CCU 1000 requires cool-
ing water supply and electrical power. The corre-
sponding requirements can be found below and in
4.1.1 Electrical Power and Computer Inter-
face
CCU 1000:
•
Mains voltage: AC 230 V ± 10 %
•
Mains frequency: 50 or 60 Hz.
•
Mains connector (1): IEC 60320 C13
•
Mains fuses: 2 x T 8 A H 5 x 20 mm (ceramic
tube)
•
Remote control interface: RS 232 C
•
RS 232 connector on CCU (2): D-Sub DE-9
(male)
•
Cable type: null modem
4.1.2 Cooling Water Requirements
•
flow rate: 0.7 to 1.5 l/min
•
temperature: 15 to 25 °C
•
pressure: max. 4 bar
4.2 Mounting the Adapter on
HTK 1200N
An appropriate
adapter
is necessary to mount the
HTK 1200N High-Temperature Oven-Chamber on a
goniometer. For detailed ordering information, refer
to
1
Alignment equipment
2
Allen screw (4 pcs)
3
Adapter (version depends on the goniometer used)
4
HTK 1200N base plate
To mount the adapter, proceed as follows:
1. Remove the alignment equipment (1) from the
rear of the HTK 1200N base plate (4).
2. If required, clean the O-ring at the adapter
flange and lightly coat the O-ring with vacuum
grease.
3. Use the four Allen screws (2) to mount the
adapter to the HTK 1200N base plate (4).
CAUTION
X-ray radiation
The HTK 1200N High-Temperature Oven-Cham-
ber represents an open system. It is only permit-
ted to install the HTK 1200N on diffractometers
equipped with a radiation enclosure.
NOTICE
Risk of damage
Do NOT touch the X-ray window
during instal-
lation. When you touch the window, the graphite
foil underneath the Kapton foil will tear.
1
2
3
4