background image

 

3

 

*Control Contacts: These connections are wired in series with the control 
line just as any other belt switch.  In order to protect the wire, 

a 15-amp in-

line fuse should be installed in series with the GREEN wire.

  The switching 

is done by a relay with either normally open (RED) or normally closed 
(BROWN) contacts.  Most control lines will need to be opened to shut down 
the belt drive.  In this case, connect the GREEN (common) and the RED 
(normally open) wires in series with the control line.  When the belt is 
running above the preset point the GREEN and RED wires will be shorted.  
A belt slip condition will cause these wires to open. 

 

 
 
 

SETUP INSTRUCTIONS

 

 

STEP 1 – SPEED 

Refer to Figure 2.  Temporarily take a jumper wire and short out the control 
wires (GREEN or RED) so that the belt will run.  Start the belt.  Turn the 
speed adjustment fully counterclockwise.  The red calibration light should 
come on.  Now start turning it clockwise until the light goes out.  At this 
point, you should back it counterclockwise about 1/8 turn to the point where 
the light just comes on.  If the belt slows from its present speed, the light 
will go out, and the relay will drop out.  Turning the speed adjustment 
clockwise raises the cutoff point (faster).  Turning it counterclockwise 
lowers the cutoff point (slower). 

 

STEP 2 – DELAY

 

Refer to Figure 2.  The delay adjustment was set fully counterclockwise (no 
delay) at the factory.  A maximum of ten seconds’ delay can be set.  Turning 
the delay adjustment clockwise increases delay, while turning it 
counterclockwise decreases delay.  Delay starts when the calibration light 
goes out.  It is instantly reset when the light turns on.   
 
 
 
 
 
 

Summary of Contents for LS-3000-220

Page 1: ...DWIDE P O BOX 234 ROCKY GAP VA 24366 PHONE 276 928 1712 FAX 276 928 1814 Email sales americanmineresearch com Visit our web site at www americanmineresearch com AMR LS 3000 220 BELT SLIP SEQUENCE CONTROL INSTALLATION AND SETUP INSTRUCTIONS 12 2 98 ...

Page 2: ...r This distance should not exceed or nuisance tripping may result Optimum distance is An indicating light is built into the rear of the module to check proper positioning and operation STEP 4 Route the cable back to the belt starter control box STEP 5 Make electrical connections as follows Input Power 220 VAC these two connections require constant 220 VAC 15 30 at 3VA to run the LS 3000 220 circui...

Page 3: ... short out the control wires GREEN or RED so that the belt will run Start the belt Turn the speed adjustment fully counterclockwise The red calibration light should come on Now start turning it clockwise until the light goes out At this point you should back it counterclockwise about 1 8 turn to the point where the light just comes on If the belt slows from its present speed the light will go out ...

Page 4: ...peed adjustment or the positioning of the module STEP 4 At the end of the module is a test switch that can be used to check that the unit is functioning properly This switch will short out the pick up coil thereby checking the entire circuitry When you push the switch the control contacts should drop out and the belt should stop Note that whatever delay you have set will be present in this test ...

Page 5: ...5 LS 3000 220 BELT SLIP SEQUENCE CONTROL WIRING IDENTIFICATION BLACK WHITE 220VAC INPUT GREEN RELAY COMMON RED RELAY NO BROWN RELAY NC ...

Reviews: