2.2.15 Fixing of optional End Mouldings. 

 
If end mouldings (P) have been ordered 
(optional item) fit the end mouldings with the 
screws provided / quick release clips to the 
holes in top of the canopy.

 

 
2.2.16 HB Manifold Assembly. 

 
VSO Models ONLY. 

After fixing the heaters in 

the desired position, the manifold system 

 

 

 

 

 

requires fitting. 
 
After allowing for a minimum of 75mm (3in) of 
penetration of the fitting into the tube, cut the 
tubes to the lengths required and remove all 
burrs and wipe off any grease or oil with a clean 
rag. 
 

Method of jointing aluminium tube 
 

Using the applicator gun exude 4mm diameter 
bead of high temperature silicon jointing 

 

 

 

 

 

compound externally round the end of the fitting 
and internally round the end of the tube.  
 
Enter the fitting into the tube using a slight    
rotating movement to spread the jointing 

 

 

 

 

 

compound uniformly until a penetration of 75mm 
(3in) is achieved. 

 
Note The silicon jointing compound remains 
workable after application for only 5 minutes. 
 

Secure the joint by drilling through the tube and 
fitting and fix with three pop rivets at 12 o’clock, 
4 o’clock and 8 o’clock positions. 4.8mm 
(3/16in) diameter pop rivets are recommended.

 

 
2.2.17 Detailed Assembly Drawings 

 

The following pages show the exploded 
diagrams of the VSO and VSXO range of 
heaters. 
 
Please  note  the  heater  type,  length  and         
reference number from the delivery/advice note   
before identifying the correct model drawing 

Fitting 

Manifold 

External bead of 
jointing compound 

Internal bead of 
jointing compound 

Manifold Tube 

Vacuum Test Point 

Damper Blade 

Emitter Tube 

FLOW 

FLOW 

Summary of Contents for Vision VSO Series

Page 1: ...1974 or relevant codes of practice In addition the installation must be carried out in accordance with the current IEE wiring regulations BS 7671 BS 6896 Industrial Commercial and any other relevant...

Page 2: ...th and Safety AmbiRad heaters must be installed in accordance with the relevant provisions of the Gas Safety Installations and Use Regulations 1998 Due account should also be taken of any obligations...

Page 3: ...ollowing tools and equipment are advisable to complete the tasks laid out in this manual Suitable alternative tools may be used 2 2 Assembly Notes refer fig s 1 7 2 2 1 Tubes Identify and position tub...

Page 4: ...he heater have been fully assembled and hung in position see Final Fixings section 2 2 7 2 3 All remaining U bolts on the RETURN TUBE should also be tightened to achieve a minimum torque setting of 15...

Page 5: ...A A A A A TWO MODULE THREE MODULE FOUR MODULE 3400mm TUBE 3400mm TUBE 3400mm TURBULATOR 976mm TURBULATOR 2600mm TURBULATOR 976mm TURBULATOR 3040mm TURBULATOR 976mm TURBULATOR 2600mm TURBULATOR 3400mm...

Page 6: ...7 1 Overshield Reflectors Overshields J1 are fitted to the underside of and run in parallel to the inner reflectors One end of the overshield has two holes for direct fixing to the reflector the other...

Page 7: ...IELD 201928 1680 OVERSHIELD 201928 1680 OVERSHIELD 201931 1200 OVERSHIELD 201931 1200 OVERSHIELD BURNER END BURNER END BURNER END AV NUT WASHER CROSS MEMBER OVERSHIELD REFLECTOR WASHER SET PIN EXPANSI...

Page 8: ...second reflector onto the same bolt using the FIRST slot in from the end and OVERLAP the first reflector This should create a 77mm overlap Secure using large washers and anti vibration nuts 5 The slot...

Page 9: ...9 Locate the fourth reflector onto the same bolts using the FIRST slot in from the end and OVERLAP the third reflector This should create a 84mm overlap Secure using large washers and anti vibration...

Page 10: ...21 Page 10 of 20 TWO MODULE THREE MODULE FOUR MODULE 114mm OVERLAP 67mm OVERLAP 77mm OVERLAP 84mm OVERLAP 77mm OVERLAP 50mm OVERLAP WASHER REFLECTOR WASHER REFLECTOR FIXING DETAIL D AV NUT Fig 3 Refle...

Page 11: ...which holds the two halves together Install the outer canopies using the following method 2 2 8 1 Two Module Units 1 Slide on the two halves to cover the 1st section of the heaters and fit closing pla...

Page 12: ...AN VIEW FROM ABOVE HEATER 30mm OVERLAP 30mm OVERLAP 30mm OVERLAP 90mm OVERLAP 30mm OVERLAP 30mm OVERLAP 55mm 35mm E SCRAP PLAN VIEW FROM ABOVE HEATER SCRAP PLAN VIEW FROM ABOVE HEATER FOURTH CANOPY TH...

Page 13: ...ly On VSXO only slide the heat exchanger assembly E1 onto the LEFT HAND TUBE when viewed from behind ensuring it is fully engaged Secure with pinch screws 2 2 13 Fan Assembly On unitary heaters only s...

Page 14: ...e end of the fitting and internally round the end of the tube Enter the fitting into the tube using a slight rotating movement to spread the jointing compound uniformly until a penetration of 75mm 3in...

Page 15: ...J2 Expansion Plate J3 Cross Member K Insulation L Outer Canopy M Canopy End Cap N Closing Plates P End Mouldings optional Ref Description A Radiant Tubes B Suspension Brackets C Return Bend D Coupler...

Page 16: ...nitary heaters E3 Damper Herringbone F1 Forced Burner VSXO F2 Induced Burner VSO G Turbulators Fig 6 Three Module drawings A B C G P J1 J2 D H J3 K L M N F1 F2 E1 E2 E3 H Reflectors J1 Overshields J2...

Page 17: ...unitary heaters E3 Damper Herringbone F1 Forced Burner VSXO F2 Induced Burner VSO G Turbulators H Reflectors J1 Overshields J2 Expansion Plate J3 Cross Member K Insulation L Outer Canopy M Canopy End...

Page 18: ...Doc No 700021 Page 18 of 20 Notes...

Page 19: ...Doc No 700021 Page 19 of 20 Notes...

Page 20: ...cleaning of the reflectors with a soft cloth and a mild detergent non solvent based cleaners only in water can be undertaken Additional removal of dust from the radiant tubes burner and heat exchange...