Quick reference guide for the installation of REhub MPPT

Step 1

 

Prepare to connect

: Keep the cables ready. Draw the PV +Ve and -Ve wires to the battery

room.   Make   provision   to   mount   the   REhub   on   a   wall   close   to   the   batteries   and   the   Inverter.
Measure   and   cut   a   6   Sqmm   cable   (RED)   for   connection   between   REhub   and   battery.   Crimp

appropriate lugs to the cable ends. 

Step 2

 

Make the Solar connections

 : Measure Open Circuit voltage, ensure it is within REhub upper

limit, make the PV -Ve connection to REhub. Connect the PV +Ve  to the PV +Ve terminal. 

Step 3

  

Make the battery connections  

: Measure the battery Voltage to make sure it is within the

operating limits  of 12V  or 24V  battery system  voltage.  Connect  the  battery  +Ve  cable  to  the
battery terminal. Connect the battery -Ve cable to battery -Ve terminal.  

Step 4  

Make the  Inverter's  AC connections

: Make sure there is no  LIVE  and Neutral Swap in  the

Inverter's input and output. Connect the Mains Input of the Inverter to REhub. After REhub screens

shows that the battery system voltage is detected, connect the AC 3 Pin plug to Mains supply.   Your
REhub installation is complete. Close the L plate once the system working is verified on the display

screen.     WAIT   till   you   see   REhub   switching   off   the   MAINS   input   to   the   Inverter   and   the   Inverter
indicates that it is in back-up mode. 

Sl no  Description

Desired Valve 

Measured 
value 

Verified 

01 

Check PV Voc Voltage using multimeter 

Less than 90V

02

Check Battery Voltage using multimeter

12V System 

(11 to 14.5V)
24V system
(22 to 29V)

03

Check the polarity of the PV wires. Connect PV 

-Ve Wire to PV port and check for tightness. 

 

04

Connect Battery  and Solar positive to  
respective terminals on REhub. Check for 

tightness. 

 

05

Connect Battery negative to appropriate 
terminal in REhub. Check for tightness

06

REhub starts up and does System detect. Verify
if correct battery Voltage is detected. 

Correct battery
system Voltage

07

Make sure that LINE and Neutral wiring in 

existing Inverter matches the Mains / house 
wiring. Connect the Inverter Mains to REhub 

and REhub to Mains input. Wait and confirm 
that REhub switches off the Mains input to the 

Inverter

11       

                               

  V3.0

User Manual`

Summary of Contents for Rehub MPPT Eco-12

Page 1: ...e Warranty Period And Terms PLEASE PRESERVE THIS DOCUMENT Scan for storing contact information in your phone http amberroot com blog category video Copyright Amberroot Systems Pvt Ltd 2020 All rights reserved Amberroot Systems Private Limited 251 252 3rd Main 3rd Cross Road JP Nagar 3rd Phase Bangalore 560078 Contact 917899396778 info amberroot com www amberroot com ...

Page 2: ...ng from handling use or treatment that are not explicitly mentioned in this manual In particular damages arising from the following causes are excluded from the warranty 1 Voltage higher than 90V across PV or battery terminals 2 Battery cables connected across PV input terminals 3 Accidental presence of liquids in the equipment or oxidation due to condensation 4 Damage resulting from falls or mech...

Page 3: ...to use REhub with efficient Pure Sine Wave output Inverters Determine the approximate Loads day time Load connected to the Inverters and match the amount of Solar panels installed so that the energy generated per day is approximately equal to the energy consumed by the loads for best results with your Solar addition REhub functions in the following manner When Batteries are discharged the batterie...

Page 4: ...MENT IS NEITHER DESIGNED NOR GUARANTEED TO SUPPLY INSTALLATIONS USED FOR VITAL MEDICAL CARE NOR ANY OTHER CRITICAL INSTALLATION ENTAILING POTENTIAL RISKS OF DAMAGE TO PEOPLE OR TO THE ENVIRONMENT We assume no responsibility for the infringement of patent rights or other third parties rights resulting from the use of the Charger Amberroot reserves the right to make any modifications to the product ...

Page 5: ... Description Comment 1 Terminal to connect Solar Ve Ensure appropriate cable size is used and ends properly crimped to avoid accidental shorts from stray strands Ensure that the input Voltage and Current String sizing do not exceed name plate ratings 2 Terminal to connect Solar Ve 3 Terminal to connect Battery Ve 4 Terminal to connect Battery Ve 5 3 PIN 15 A Plug to connect AC input from Mains Con...

Page 6: ...PV string To get the required charging power 2 or more strings are usually to be connected in parallel Each string connected in parallel must be composed by the same number of modules of the same type The number of strings connected in parallel depends on the Isc of each string When you need to determine the Isc of the parallel array it is the Isc of each panel multiplied by the number of parallel...

Page 7: ...t a Voltage approximately equal to the open circuit voltage of the array Note if the installation is being done in the night you will not get the Voc value but likely to get a Voltage which is much lesser C Complete the Battery GND to Inverter connections and the AC live from Mains connection Switch on the AC MCB Put the Inverter to normal mode Take care not to Swap Solar PV and Battery connection...

Page 8: ...f the batteries is below a set value As a user you can decide to OVERRIDE the decision of REhub by forcing REhub to keep the Mains switch ON In ONAlwas For On Always mode REhub keeps the Mains ON at all times In ON1Day for ON One Day mode REhub keeps REhub ON for the next 24 Hours and goes back automatically to Auto Mode at the end of 24 Hours In OFF Grid mode REhub continues to keep the Mains inp...

Page 9: ...t Trip Reduce PV Capacity Wait Internal Error due to transients arising due to long battery cables Error in System Prot Trip Batt Prot Trip Reduce battery Cable length Wait Internal Error due to transients arising due to insufficient wire gauge Error in System Prot Trip Connect proper gauge wire Over temperature The unit cycles through Charging and Tripping Error in System High Temperature Wait fo...

Page 10: ...ar Charger to enable addition of Solar PV to existing home inverters Maximizes the usage of Solar Recommended Solar module STC Wp Output Current Continuous Max PV Open Circuit Voltage VOC Power Conversion Efficiency typical Ports 1PV Ve input 1PV Ve input 1Battery Ve Input 1Battery Ve 1 15A and 6A 3 Pin Socket 1 6A 1 Meter long wire with 3 Pin Plug 1 Mode Switch 1 Modbus port 16 X2 Backlit charact...

Page 11: ...b screens shows that the battery system voltage is detected connect the AC 3 Pin plug to Mains supply Your REhub installation is complete Close the L plate once the system working is verified on the display screen WAIT till you see REhub switching off the MAINS input to the Inverter and the Inverter indicates that it is in back up mode Sl no Description Desired Valve Measured value Verified 01 Che...

Page 12: ...12 V3 0 User Manual Wiring Drawing ...