46
3.2.6
Check bias interconnection _____________________________________________
3.2.7
If required check 3 phase tripping _______________________________________
3.2.8
On load tests
Load conditions
Measured differential current
__________
__________
__________ A
3.2.9
Magnetizing current inrush test _________________________________________
_________________________________
__________________________________
Commissioning Engineer
Customer Witness
_________________________________
__________________________________
Date
Date