Cut a hole and/or remove tiles so that there is at least a 150

mm diameter hole in the roof. Ensure there is at least a 25

mm gap between the outer duct and any combustible

material.

c.

Fit a 125 mm diameter weathering slate over the hole in the

roof. A suitable weathering slate (Part No. 6.1000380) is

available from Alpha Therm Ltd.

d.

Position the vertical terminal assembly into the weathering

slate ensuring that the slate is located under the lip of the

terminal as shown in Fig. 3.

Note:

Ensure that the minimum distances are maintained

(see Fig. 4). Do not secure the terminal into position at this

stage.

e.

Assemble the flue ducts together and cut the outer air duct

and inner flue duct assemblies to the correct lengths, i.e. up

to the terminal.

f.

Place the inner duct into the outer duct and fit the ducts to

the boiler, as shown in Fig. 3, using the clamps supplied.

g.

Connect the terminal ducts to the flue assembly, as shown

in Fig. 3. Secure the inner ducts with the clamps supplied

before locating the outer duct clamp.

h.

After assembling all of the ducts, check that the terminal is

correctly located above the roof.

Note:

Ensure that the flue assembly is supported at roof

level using suitable brackets, and that the weathering slate

is fitted correctly.

Fig. 3

These instructions have been carefully prepared but we reserve the right to

alter the specification at any time in the interest of product improvement.

© Alpha Therm Limited 2004.

Alpha Therm Limited.

Nepicar House, London Road, Wrotham Heath,

Sevenoaks, Kent  TN15 7RS