This section contains instructions to the second part of configuring the
member switch. The instructions explain how configure the following
parameters:
Set the priority number. For background information, refer to
“Selection of the Master Switch” on page 59.
Designate the ports of the stack trunk. Refer to “Stack Trunks” on
page 50.
To configure the member switch, perform the procedure in Table 19.
10
Restart the switch with the REBOOT command.
awplus# reboot
reboot system? (y/n):
awplus#
11
Type “Y” for yes.
12
Wait two minutes for the switch to initialize its management software.
13
Check the ID LED on the front panel and do one of the following:
- If the ID LED is displaying the number 2, VCStack is now enabled on the switch. Go
to “Configuring the Member Switch - Part II,” next.
- If the ID LED is displaying a different number, repeat this procedure. Be sure to
correctly enter the STACK RENUMBER command and to save your changes with
the WRITE command.
- If the ID LED is displaying “0,” VCStack is still disabled. Repeat this procedure. Be
sure to perform the STACK ENABLE command and to issue the WRITE command.
Table 18. Configuring the Member Switch - Part I (Continued)
Step
Description and Command
Table 19. Configuring the Member Switch - Part II
Step
Description and Command
1
Start a new local management session on the member switch. Refer to “Starting a
Local Management Session” on page 127.
2
Enter the ENABLE command to move from the User Exec mode to the Privileged
Exec mode.
awplus> enable
3
Move to the Global Configuration mode with the CONFIGURE TERMINAL command.
awplus# configure terminal
Enter configuration commands, one per line. End with CNTL/Z.
Summary of Contents for AT-x950-28XSQ
Page 8: ...Contents 8 ...
Page 12: ...Tables 12 ...
Page 16: ...Preface 16 ...
Page 62: ...Chapter 2 Virtual Chassis Stacking 62 ...
Page 80: ...Chapter 3 Beginning the Installation 80 ...
Page 90: ...Chapter 4 Installing Power Supplies and Optional XEM2 Line Card 90 ...
Page 102: ...Chapter 6 Installing the Switch in an Equipment Rack 102 ...
Page 118: ...Chapter 7 Installing the Switch on a Wall 118 ...
Page 146: ...Chapter 8 Configuring Switches for Stacking 146 ...
Page 158: ...Chapter 9 Cabling the Networking Ports 158 ...
Page 180: ...Chapter 11 Troubleshooting 180 ...