background image

8

CHILLED WATER CASSETTE

4.4  CASSETTE INSTALLATION

Side openings are provided for installing separate ducts for 
outside air intake and treated air distribution to an adjacent 
room.
Use a punch to remove the condensation protection insulation 
and the pre-punched panels from the openings.

TAKE CARE not to damage the heat exchanger coil  
located behind the openings.

Plug the gaps between the ducts and the opening edge with 
anti-condensation insulation.
Use material which can withstand a continuous operating 
temperature of 60° C. The ducts can be of the flexible type 
with  a  spring  core  or  of  corrugated  aluminium,  covered 
inside with an insulating material (12 to 25 mm thick glass 
fibre).

If it is indented to install ducting to an adjacent room, refer to § 

4.4

 for 

removal of the pre-punched panel before installing the cassette.

4.3  CASSETTE FITTING

To    make  the  assembly  easier  the  electrical  box  can  be 
disassembled  by  removing  2  screws,  and  disconnect  the 
multipoints  connectors  (15  pts  connector  for  the  main 

connection, 12 pts connector for the electric heating) and 
small connector for the infra-red.
Fix the cassette, connect the multipoints connectors, place 
the cassette into is final position and reset the electric box 
with 2 screws

 Fix the screws to fix the corner irons
In the event that the suspended ceiling is 300 mm from the 
ceiling (minimum permitted height), it might be necessary 

to  temporarily  remove  some  of  the  suspended  ceiling  T 
supports.
Position  the  cassette  on  the  suspended  ceiling  support 
rods, and start by tightening the side mounting bolts, then 
the threaded rods nuts and lock nuts, after having set the 
cassette level, maintaining a gap of around 10 mm between 
the metal chassis and the suspended ceiling.

Decompression grille

When  the  installation  is  finished,  all  the  surfaces  of  the 
non-insulated ducts must be covered with anti-condensation 
insulation material (6 mm thick expanded polystyrene or 
expanded neoprene). Fireproofing classification: M1)

IF THE ABOVE INSTRUCTIONS ARE NOT FOLLOWED, 
CONDENSATE LEAKS MAY OCCUR.

Distributing air to an adjacent room requires one or two 
of  the  corresponding  ducts’  air  distribution  flaps  to  be 
closed.
A decompression grille must be fitted in the partition between 
the air conditioned room (where the cassette is installed) 
and the adjacent room.

New air 

intake

Treated air 

distribution

WARNING !

4

 

I

NSTALLATION

 

CONTINUED

Summary of Contents for K 30 OG 2T

Page 1: ...anuel d installation et de maintenance Installations und Wartungshandbuch Manuale di installazione e di manutenzione Manual de instalaci n y de mantenimiento English IOM KOG 02 N 3ALL Part number Code...

Page 2: ......

Page 3: ...INSTALLATION INSTRUCTION NOTICE D INSTALLATION INSTALLATIONSHANDBUCH ISTRUZIONI INSTALLAZIONE INSTRUCCIONES DE INSTALACI N...

Page 4: ...S 2T 10 THERMOSTAT INSTALLATION 10 WATER TEMPERATURE PROBE INSTALLATION 10 6 3ELECTRIC HEATING 11 6 4FAULT WARNING REPEATER 11 6 5VENTILATION SPEEDS 11 6 6WIRING DIAGRAM 11 7 ELECTRICITY 12 7 1THERMOS...

Page 5: ...E SWITCHED OFF BEFORE STARTING ANY WORK ON CONTROL BOXES The aim of this manual is to provide cassette users with instructions for installation commissioning operation and maintenance It does not cont...

Page 6: ...ENSIONS 2 3 WEIGHTS 2 DESCRIPTION 1 Documentation bag 1 Fascia assembly Dimensions in mm 1 Suspended ceiling 2 T bar suspended ceiling 3 Evaporator 4 Fan 5 Intake grille 6 Electrical connection 7 Cond...

Page 7: ...eiling 3 Evaporator 4 Fan 5 Intake grille 6 Electrical connection 7 Condensate evacuation 15 8 Hot water outlet RC1 2 8a Hot water intake RC1 2 9 Cold water outlet RC1 9a Cold water intake RC1 10 Open...

Page 8: ...in its packaging until it is to be finally installed DO NOT LIFT THE CASSETTE BY THE CONDENSATE EVACUATION TUBE The sharp edges and surfaces of the coils can cause injury Avoid contact with them Minim...

Page 9: ...nal horizontal position when are the connections have been completed 4 2 CEILING MOUNTING Mark the position of each support rod Refer to Chapter 2 Dimensions The cassettes must not be positioned above...

Page 10: ...infra red Fix the cassette connect the multipoints connectors place the cassette into is final position and reset the electric box with 2 screws Fix the screws to fix the corner irons In the event th...

Page 11: ...easant odours in the room 5 2 HYDRAULIC CONNECTIONS For the system to operate in complete safety regulating valves must be fitted if they are not already fitted at the factory The regulation valves ar...

Page 12: ...winter or with chilled water in summer and during the mid season periods A 3 way valve must be installed on the water circuit supplying the unit Summer and mid season The 3 way valve is controlled by...

Page 13: ...ght I max 4A 250 V can be connected to terminal 6 230 V NEUTRAL potential Provide electrical supply to the system on the same phase and coming from the same circuit protection device as the cassette M...

Page 14: ...thermostat is located in the room s normal thermal currents and that it is not located in shelving or covered by curtains Any source of parasitic heat negatively influences temperature regulation acc...

Page 15: ...the operating time Liquid crystal diode display BACK LIGHT OPTIONAL I FEEL sensor Infrared signal transmitter ROOM key display of the ambient temperature LOCK key SET key Press for 5 seconds to set t...

Page 16: ...ENSIONS WALL MOUNTING Remove the thermostat control knob the screw and the cover On a flat surface mount the control panel using plugs and screws Install the cover the screw and the thermostat control...

Page 17: ...a n g e e g max 25 C min 12 C Remove the control knob Use a pointed object to align the mark on the red ring max value with the desired maximum temperature 25 C turning the red index opposite the out...

Page 18: ...stened The screw terminal connections are located on the mounting plate with the DIP switches on the back of the case ADJUSTMENT AND CONTROL ELEMENTS Operatingmodeswitch ON OFF andmanual fan speed sel...

Page 19: ...ing distributed into the suspended ceilling space After installation check that the gap between the frame and the suspended ceiling is less than 5 mm 5 mm install the central grille by twisting Avoid...

Page 20: ...For the installation to operate correctly it is imperative that the air filter located on the air intake of the treated air coil is cleaned regularly Check the connections seals and if required insul...

Page 21: ...APPENDIX ANNEXE ANLAGE ALLEGATO ANEXO APPENDIX ANNEXE ANLAGE ALLEGATO ANEXO...

Page 22: ...APPENDIX ANNEXE ANLAGE ALLEGATO ANEXO II...

Page 23: ...ferten Stromlaufplan hinzuziehen ATTENZIONE Questi schemi sono corretti al momento della pubblicazione Le varianti apportate nel corso della fabbricazione possono comportare modifiche Far sempre rifer...

Page 24: ...APPENDIX ANNEXE ANLAGE ALLEGATO ANEXO IV 30 2T 30 4T 45 2T 45 4T SANS VANNE...

Page 25: ...APPENDIX ANNEXE ANLAGE ALLEGATO ANEXO V 30 2T AVEC CHAUFFAGE SANS VANNE...

Page 26: ...APPENDIX ANNEXE ANLAGE ALLEGATO ANEXO VI 45 2T AVEC CHAUFFAGE SANS VANNE...

Page 27: ...APPENDIX ANNEXE ANLAGE ALLEGATO ANEXO VII 4 6 1 2 3 4 ALARM EH2N F H F L F M L N RAT WIN VL1 VL1N VL2 VL2N UNOC WPT 30 2T 30 4T 45 2T 45 4T AQUANET...

Page 28: ...PIPE AQUANET CASSETTE AGUA HELADA 2 TUBOS AQUANET 10 9 BK CASSETTE ACQUA GHIACCIATA 2 TUBI AQUANET L1 L2 L3 8 9 10 X X L1 53 54 55 56 3 L1 7 18 7 7 N N 15 16 17 2 1 12 13 13 L1 L1 11 12 BU 2 OPTIONS L...

Page 29: ...FREDDO RISCALDO BASSA VELOCIT VELOCIT MEDIA ALTA VELOCIT BATER AS 2 TUBOS BATER AS 4 TUBOS FRIO CALOR VELOCIDAD BAJA VELOCIDAD MEDIA VELOCIDAD ALTA SCH SW ELECTRIC HEATING CONTROL VALVE CHANGE OVER T...

Page 30: ...DIX ANNEXE ANLAGE ALLEGATO ANEXO X SCH S TAE20 L L1 N 3 4 5 6 7 L N Q3 Q2 Q1 Y11 Y21 SCH M B2 2T S TAE20 L L1 N 3 4 5 6 7 L N Q3 Q2 Q1 Y11 Y21 M B2 2T S TAE20 L L1 N 3 4 5 6 7 L N Q3 Q2 Q1 Y11 Y21 M B...

Page 31: ...APPENDIX ANNEXE ANLAGE ALLEGATO ANEXO XI S TAE20 L L1 N 3 4 5 6 7 L N Q3 Q2 Q1 Y11 Y21 M B2 4T S L L1 N 3 4 5 6 7 6 N 3 4 5 2 1 2T TRM VP SCH S L L1 N 3 4 5 6 7 6 N 3 4 5 2 1 SW YF 2T TRM VP...

Page 32: ...APPENDIX ANNEXE ANLAGE ALLEGATO ANEXO XII S L L1 N 3 4 5 6 7 6 N 3 4 5 2 1 2T TRM VP S L L1 N 3 4 5 6 7 6 N 3 4 5 2 1 2T TRM VP S L L1 N 3 4 5 6 7 6 N 3 4 5 2 1 2T TRM VP...

Page 33: ...APPENDIX ANNEXE ANLAGE ALLEGATO ANEXO XIII S L L1 N 3 4 5 6 7 6 N 3 5 4 2 1 4T TRM VP S L L1 N 3 4 5 6 7 4 N 1 2 3 6 8 7 2T TRM FA SW S L L1 N 3 4 5 6 7 4 N 1 2 3 6 8 7 SW YF 2T TRM FA...

Page 34: ...APPENDIX ANNEXE ANLAGE ALLEGATO ANEXO XIV S L L1 N 3 4 5 6 7 4 N 1 2 3 6 8 7 2T TRM FA S L L1 N 3 4 5 6 7 4 N 1 2 3 6 8 7 2T TRM FA S L L1 N 3 4 5 6 7 4 N 1 2 3 6 8 7 2T TRM FA...

Page 35: ...APPENDIX ANNEXE ANLAGE ALLEGATO ANEXO XV S L L1 N 3 4 5 6 7 4 N 1 2 3 6 8 7 4T TRM FA L L1 N 3 4 5 6 7 4 N 1 2 3 6 8 7 2T TRM FA 2T 2T...

Page 36: ...APPENDIX ANNEXE ANLAGE ALLEGATO ANEXO XVI...

Page 37: ...ROMAGNETICA 89 336 CEE ENMENDATA POR LA DIRECTIVA 92 31 CEE Y 93 68 CEE DIRECTIVA DE LOS EQUIPOS A PRESION DESP 97 23 CEE BAJA MODULO A CATEGORIA I D claration CE de conformit Nous d clarons sous notr...

Page 38: ...um st ndige Verbesserung k nnen unsere Erzeugnisse ohne vorherige Ank ndigung ge ndert werden Fotos nicht vertraglich bindend A causa della politica di continua miglioria posta in atto dal costruttore...

Reviews: