Commissioning Procedure
GENERAL
To be read in conjunction with the commissioning sheets provided, items highlighted
should be recorded.
new
CAUTION
Please ensure all documents have been completed correctly and return to Airedale
Service immediately to validate warranty.
new
PRE COMMISSIONING CHECKLIST
new
ALL work MUST be carried out by Technically Trained competent personnel.
new
CAUTION
The equipment contains live electrical and moving parts, ISOLATE prior to
maintenance or repair work.
new
Prior to carrying out the following, in order to prevent liquid entering the
compressor whilst the mains MCCB are in the OFF position, isolate the liquid
injection and liquid line solenoid valves at the terminal blocks (located above the
bus bar).
new
The door interlocking MCCB should be in the OFF position and the auxiliary alarm
contact from the MCCB should be linked out.
new
Ensure all items listed in the Pre commissioning section are complete.
new
RECORD
•
The unit should be visually inspected and any damage noted.
•
Secure commissioning gauges to the high side of the system, check for a
positive charge.
•
Check tightness of electrical components.
•
Check that the remote on/off switch (if fitted) is in the off position.
•
With the MCBs in the off position measure the incoming voltage.
•
Check Phase Rotation.
•
Check voltage at permanent supply.
•
Measure and record the primary (230V) and secondary (24V) voltages at each of
the transformers and record on the commissioning document.
•
Check all timer settings are correct.
•
Check Sump Heater.
•
Check oil level.
•
Check water filter is fitted.
•
Check design water flow is available.
•
Check flow switch and pump interlocks are fitted to the water system.
•
Switch on the controls and individual circuits, primary and secondary, MCBs to the
ON position. At this stage the control display panel should be illuminated.
•
Record Optional Extras.
•
Record IQ Controller Data.
new
CAUTION
The chiller will not start until microprocessor control SWITCH 1 is in the ON
position. DO NOT SWITCH TO ON AT THIS STAGE
new
•
Adjust the water temperature supply and return set points (if necessary) to call for
100% cooling (refer to the
Control Section
).
new
•
Ensure all KNOBS and SWITCHES are adjusted to suit the design requirements
(refer to the
Control Section
).
new
•
Turn the unit on by setting SWITCH 1 to enable unit to ON.
new
CAUTION
There will always be a delay between the enabling of the unit and the energising of
the compressor contactors, anything between 1 to 2 minutes. Be patient, refer to
Control Section.
new
•
Check that there is a 5 seconds delay between the Star and Delta contactor
energising on each circuit.
new
This delay period would be 0.7 seconds in Closed Transition Starting.
new
CAUTION