6.  Repeat this process until there are 4setsof full curves created. 

7.  Using 4 Opto Joints connect the Top curves together, 

as shown in Figure 2. 

8.  The easiest way to ensure that the full curves are 

connected evenly is to haveoneor2peoplealign the 

curves to form theshapeshowninfigure2, with the 

straight part of the curve resting on the floor. Once the 

curves are held in position another person should 

connect the top curves atthe11 and1o’clock positions, 

using the Opto Joints. 

9.  Once completed the curves will form a structure as 

Shown in Figure3. 

Figure2: Aerial View of the Gazebo Full Curves

 

Connecting

 

 

 

 

 

 

 

 

 

 

 

 

 

Attach the Stafford Curves…

 

Figure3: Gazebo Curves once connected

 

10. Tap an end plug into the ends of the Stafford curves, repeat this action with all 4 Stafford 

curves. 

11. Attach, using Opto Joints, the Stafford Curves in the gaps between the Top Curves. Leave 1” 

of the Stafford curve protruding from theclamp.Theclampshouldbepositioned1” from the 

bottom of the Round Curves, as illustrated in Figure 4. 

12. Ensure that once you have completed the construction of the Gazebo top, that you check 

the distance between the ends of the curves are equal. 

 

 

Figure4: Positioning of the Stafford Curves                                                                                  Figure5: Aerial View of Completed Gazebo Top

 

If the distances are not equal adjust, as 

Necessary, the clamps’ positioning on the Top Curves (refer toFigure1), and tighten 

the clamps.  

 
 
 

  

 

Summary of Contents for 40540-TB

Page 1: ...Grub screws in a separate bag 1Bag AGR A610 38 1 Moisture Seal 16 AGR A610 08 1 EndPlug 16 AGR A70 006 AGR A70 009 3mmAllenKey 6mm Allen Key 1 AGR A622 07 Op to Parallel Joint Coated Two Halves with Nut Bolt 12 Issues If you are experiencing any issues with your Agriframes product please contact our customer services team on0117 934 1790 and quote your order reference WARNING Contains small parts ...

Page 2: ... the correct distance between bars Lattice Panel Option For illustrative purposes we have only shown one side fixed with the lattice panels Attach panels to both sides as you proceed 1 Before assembly check Spacer Bars to ensure the grub screws are inserted into the holes on the ring clamps o Loosen these grub screws way out of the hole to ensure when the ring clamps are moved into position the gr...

Page 3: ...tructure as Shown in Figure3 Figure2 Aerial View of the Gazebo Full Curves Connecting Attach the Stafford Curves Figure3 Gazebo Curves once connected 10 Tap an end plug into the ends of the Stafford curves repeat this action with all 4 Stafford curves 11 Attach using Opto Joints the Stafford Curves in the gaps between the Top Curves Leave 1 of the Stafford curve protruding from theclamp Theclampsh...

Page 4: ...acer bar as shown in Figure 6 18 Slide a moisture seal onto the reduced end of the upright Lift the Top of the Gazebo onto the uprights 19 Lift the constructed Gazebo Top onto the uprights ensure that the Gazebo Top is lowered evenly onto the uprights 20 Cover the Joins with moisture seals Final checks 21 Check that all of the joins have been covered by moisture seals 22 Ensure that all of the con...

Reviews: