-  Install the unit at a distance enough from the exhaust wells, to ensure 

that the possible loss of gas may reach and pollute the aquifer

-  Keep all lubricants in properly marked containers do not keep 

flammable liquids near the plant 

-  Do not remove the protections from mobile elements while the unit 

is running 

-  Do not use cables with inadequate section or flying connections, not 

even for limited periods or emergencies 

-  Check the unit is properly earthed before starting it 

-   Before opening the electrical panel, disconnect the unit from the 

mains by means of the external isolator 

-  In case of units with shunt capacitors, wait 3 minutes from when 

power supply was disconnected from the unit before accessing inside 

the electrical panel 

-  If the unit is equipped with integrated inverter compressors, 

disconnect the power supply and wait at least 15 minutes before 

accessing for maintenance: the internal components remain live for 

this time, generating the risk of electrocution 

-  The safety devices must be maintained efficient and periodically 

checked as prescribed by current regulations 

-  In case a piece is disassembled, make sure it is correctly reassembled 

before restarting the unit 

-  Even with the unit off, prevent the fluid in contact with the 

heat exchangers exceed the temperature limits indicated in the 

documentation and freeze.

-  Do not send the heat exchangers fluids other than water or its 

mixtures with ethylene glycol/propylene in a maximum concentration 

of 30% 

-  The machine must only be employed for the use for which it was 

made; any other use can be dangerous and void the warranty

P

REVENTIONS

-  Make sure that the protections of mobile elements are correctly in 

place before restarting the unit 

-  Fans, motors and belt drives may be in motion: always wait for them 

to stop and take appropriate precautions to prevent their activation 

before accessing them 

-  The machine and the pipes have very hot and very cold surfaces that 

lead to risk of burns

-  Before opening a machine panel, ascertain whether it is or not firmly 

connected to it by hinges 

-  Louvers of the heat exchangers, edges of the components and metal 

panels can generate cuts

 -  The installation must ensure that the temperature of the fluid 

entering the unit is maintained stable and within the provided limits; 

therefore, pay attention to the adjustment of any external thermal 

exchange and control devices (drycooler, evaporating towers, 

area valves, ...), to the adequate dimensioning of the mass of fluid 

circulating in the plant (in particular when plant areas are excluded) 

and to install systems for the recirculation of the necessary fluid flow 

rate so as to maintain the machine temperatures within the allowed 

limits (e.g. during the start-up phase). 

-  The material used for the machine protective packaging must always 

be kept out of the reach of children as it is a source of danger 

-  In units with compressors in parallel, do not disable the individual 

compressors for long periods.

-  This is an appliance not accessible to the general public.

Summary of Contents for NYB

Page 1: ...l a t i o n f r o m o r i g i n a l I n s t a l l a t i o n m a n u a l EN 60Hz AIR WATER CHILLER AND AIR WATER CHILLER WITH FREE COOLING C o o l i n g c a p a c i t y 2 8 9 7 t o n 2 8 4 6 t o n NYB...

Page 2: ......

Page 3: ...inuous changes in the market and its regulations reserves the right to make all the changes deemed necessary for improving the product including technical data Thank you again AERMEC S p A This markin...

Page 4: ...ht distribution 12 Hydraulic connections 13 Water features 13 Hydraulic circuits 14 Internal and external hydraulic circuit NYB 14 Water features 14 Electrical connections 15 Electrical data of the un...

Page 5: ...20 05 4138421_03 5 CERTIFICATIONS COMPANY CERTIFICATIONS COMPANY CERTIFICATIONS SAFETY CERTIFICATIONS...

Page 6: ...ssary repairs The installation must comply with the requirements of EN378 3 and the local current regulations In particular indoor installation must ensure adequate ventilation and provide refrigerant...

Page 7: ...r its mixtures with ethylene glycol propylene in a maximum concentration of 30 The machine must only be employed for the use for which it was made any other use can be dangerous and void the warranty...

Page 8: ...ed pre loaded with refrigerant make sure there have been no leaks Check that the equipment supplied corresponds to the order and delivery note Product identification The Aermec products can be identif...

Page 9: ...NSTALLATION The chiller is shipped already tested and only requires electrical and hydraulic connections in the installation site Before beginning the installation process decide with the client where...

Page 10: ...ny case make sure that the anti vibration supports rest at on the base surface It is essential that the units are installed leaving su cient space around them to allow easy access to the components fo...

Page 11: ...20 05 4138421_03 11 DIMENSIONS MINIMUM TECHNICAL SPACES NYB Vers A1 B1 B2 C1 C2 in in in in in 0500 A 118 79 59 47 in ELECTRICAL BOX C2 B2 C1 B1 A1 96 5 in 86 7 in 6 6 in 46 9 in 9 9 in 11 9 in 5 0 in...

Page 12: ...option Empty 2 046 24 0 40 4 26 27 23 24 Running 2 213 24 0 43 4 24 26 24 26 Freecoolingversion optionF Empty 2 672 23 7 41 6 26 26 24 24 Running 3 007 23 7 43 9 24 25 25 26 ATTENTION For installatio...

Page 13: ...he environment temperature drops below 0 C insulate the pipes and provide an electric heater As an option you can also protect the pipes inside the unit Check the continuity of the earthing ATTENTION...

Page 14: ...vibrationjoints 7 Airdrainvalve 8 Pump 9 Drainvalve 10 Pressuregauge 11 Flowshut offvalves 12 Expansionvessel 13 Safetyvalve 14 Loadingunit 15 Storagetank 16 Anti freezeelectricheater 17 Flowswitch MA...

Page 15: ...ection The manufacturer cannot be considered responsible for any damage caused by the lack of or ineffective appliance earth connection For units with three phase power supply check the correct connec...

Page 16: ...M A 228 MCA M A 74 MOP M A 100 Power supply 575V 3 60Hz LRA J A 167 MCA J A 61 MOP J A 80 LRA M A 171 MCA M A 65 MOP M A 80 Size NYB free cooling Fans 0500 Power supply 208V 3 60Hz LRA J A 434 MCA J A...

Page 17: ...e that all protections removed for the electric connection have been restored before powering the unit electrically Close all the opened panels Turn the switch at ON position Position the system maste...

Page 18: ...les present in this manual Check the correct functioning of the ow meters if installed Closing the cut off valve at the output of the heat exchanger the unit control panel must show the block Finally...

Page 19: ...event their activation before accessing them Isolate the unit from the mains by means of the external isolator provided for the insertion of padlocks up to 3 for blocking in open position Place a sign...

Page 20: ...e replaced after draining the refrigerant gas contained in the circuit During venting protect yourself against any leakage of uids at dan gerous temperatures and or pressures Always use appropriate eq...

Page 21: ...f The high low pressure switch where present must be tested with the machine closed reading the high pressure circuit pressure on the machine control panel In case of machines with the cooling circuit...

Page 22: ...ts paying particular attention to under pres sure containers In this case replace them of intervene with specific products General cleaning of the unit Bleed the hydraulic circuit and the heat exchang...

Page 23: ...roper functioning of the thermostatic valve Check the charge of refrigerant gas 1 Check the proper functioning of the solenoid valves MAINTENANCE LIST OF THE RECOMMENDED PERIODIC INTERVENTIONS DECOMMI...

Page 24: ...0 B e v i l a c q u a V R I t a l y P h o n e 3 9 0 4 4 2 6 3 3 1 1 1 F a x 3 9 0 4 4 2 9 3 5 7 7 s a l e s a e r m e c c o m w w w a e r m e c c o m DOWNLOAD THE LATEST VERSION http www aermec com q...

Reviews: