5. POST INSTALLATION CONNECTIONS AND ADJUSTMENTS
Figure 5-2 shows a typical DW-68 Double Wall S/W Heater with all ECS and CXT-E Retrofit items
installed. Upon completion of all retrofit procedures in Section 4, the ECS Retrofit heater must be
thoroughly checked to ensure that all required external connections have been made to the
modified Heater. In addition, CXT-E Actuator and ECS Control system adjustments must be made
prior to placing the Heater back into service.
5.1
INPUT AND OUTPUT WATER HEATER CONNECTIONS
The following items must be checked to ensure the proper connections have been made:
1.
Drain Connection
: Ensure that the Drain Ball Valve has been replaced and that all
external drain piping is reconnected.
2.
Cold Water Inlet
: Ensure that the Cold Water Inlet Flange is connected to the cold water
inlet piping.
3.
Steam Line
: Ensure that the Steam supply line is connected to the inlet of the CXT-E
Control Valve.
4.
Condensate Line
: Ensure it is connected to a nearby drain or condensate collection
system.
5.
Electrical Power
: Ensure that AC power (120 to 240 volts) is connected to the ECS
Control Box.
5.2
ADJUSTMENTS
Prior to placing the unit into operation, the CXT-E Actuator, ECS Temperature Controller and ECS
Over-Temperature Switch must be set. The adjustment procedures for these items are provided in
Section 3 of Operation and Maintenance Manual HE-111. A copy of this manual is included in the