INSTALLATION, OPERATION & MAINTENANCE
4-2
4.6 SYSTEM FILLING & DRAINING
•
For filling-up the system a filling tap has to be inserted on the system return pipe.
•
The filling-up can also be made through the draining tap on the boiler return manifold.
•
In both cases, an approved hydraulic disconnection system has to be fitted.
•
Before connecting the boiler, carefully rinse out the whole system with running water.
4.7 NOTES ON CONDENSATE DRAIN
To maintain proper flow of condensate the drain pipe must slope toward the drain of at least 3/8 in./ft.
(30 mm/m). The liquid column inside the condensate siphon needs to be filled with water after
installation. Its minimum height when all the fans are in operation must be at least 1 in. (25 mm). See
Figure 4-1. In order to help avoid ice from forming, the condensate piping system must be well
insulated.
DO NOT INSTALL THE CONDENSATE DRAIN WHERE FREEZING MAY
OCCUR.
Consult local codes with regard to condensate neutralization. Neutralization can be obtained by mixing
it with the buildings drain water or with limestone, which normally have a base pH.
Figure 4-1
Typical Condensate Drain Installation
4.8 GAS MAINS AND CONNECTIONS
•
Connect gas service meter to control assembly in accordance with the current version of the
ANSI Z223.1 and the local codes or utility.
•
Prior to operation, the complete gas train must be leak tested using a non-corrosive soap.
•
For gas pipe sizing and additional details, see GF-115-P-H.
Summary of Contents for Modulex 1060
Page 16: ......
Page 25: ...INSTALLATION OPERATION MAINTENANCE 2 9 Figure 2 7 Sample Data Plate ...
Page 33: ...INSTALLATION OPERATION MAINTENANCE 5 3 Figure 5 2 ...
Page 34: ......
Page 44: ......
Page 51: ...APPENDIX A A 1 APPENDIX A Temperature Sensor Resistance Charts ...
Page 53: ...APPENDIX B B 1 APPENDIX B Modulex Parts List ...
Page 54: ...APPENDIX B B 2 ...
Page 55: ...APPENDIX B B 3 ...
Page 56: ...APPENDIX B B 4 ...
Page 58: ......