DESCRIPTION

The FD3-PMFC06, shown in 

Figure 1

, is a stainless steel frame that provides a mounting base

for the small size FDH 3000 cabinet when installed in a concrete pad foundation. 

Figure 1. FD3-PMFC06 Dimensions

2

INSTALLATION RECOMMENDATIONS

The site chosen for the installation must conform to all local codes and any permits required
must be obtained prior to the start of installation. The location must be accessible and provide
adequate parking for worker and vehicle safety. Situate the concrete pad along the trench that
was used for routing the OSP fiber cables for the system. The installed cabinet must not create a
visual or physical obstruction to vehicular or pedestrian traffic. Ensure that there is sufficient
space on all sides to facilitate cabinet installation. Depending on the landscaping requirements,
the top surface of the concrete pad may be located from 0 to 3 inches (7.6 cm) above the
surrounding grade. 

3

BASE CONSTRUCTION AND CONDUIT INSTALLATION

Prepare a base for the concrete pad that meets all local code requirements. The base must have a
footing of 4 to 6 inches (10.2 to 15.2 cm) of gravel or other suitable fill (per local practice) on
firmly compacted soil. Refer to the diagram shown in 

Figure 2

 for the base construction details. 

Caution: 

Mounting the cabinet directly on a concrete pad may cause chemical corrosive action

to the cabinet. Use only the Pad Mount Frame (PMF) as a mounting base for the cabinet. Do
not use caulking compounds as a sealer between the cabinet and the PMF. 

Note: 

Use crushed rock 3/8-inch or less in size mixed with stone dust (per local practice)

to for the base. The name of the material may differ in different geographical areas.
Possible names are Class 5, stone dust, aughts (0s) and ones (1s), or stone aggregate

21935-A

20.80 IN.

(52.8 CM)

12.55 IN.

(31.2 CM)

5.5 IN.

(14.0 CM)

Summary of Contents for OmniReach FDH 3000

Page 1: ...EM INSTALLATION 6 6 CUSTOMER INFORMATION AND ASSISTANCE 7 _________________________________________________________________________________________________________ INTRODUCTION This publication descri...

Page 2: ...and are listed in descending order of severity of injury or damage and likelihood of occurrence PAGE IDENTIFIER DESCRIPTION OF CHANGE Original Danger Danger is used to indicate the presence of a hazar...

Page 3: ...ation Depending on the landscaping requirements the top surface of the concrete pad may be located from 0 to 3 inches 7 6 cm above the surrounding grade 3 BASE CONSTRUCTION AND CONDUIT INSTALLATION Pr...

Page 4: ...for the FDH 3000 Small Size Cabinet REINFORCED CONCRETE PAD 6 0 IN 15 2 CM 4 0 IN MIN 10 2 CM GRAVEL OR EQUIVALANT FILL COMPACTED SOIL 21936 A 90 BEND IN DUCT PAD MOUNT FRAME CAST IN PLACE 4 IN DUCT F...

Page 5: ...to construct the concrete pad 1 Build a wood form for the concrete pad using 2 x 6 framing lumber as shown in Figure 4 2 Locate the PMF using the dimensions provided in the construction diagram see F...

Page 6: ...electrical codes Check local codes for grounding system installation use of clamps wire size and any other grounding requirements Typically 6 AWG copper wire is used for the ground wire If the ground...

Page 7: ...123 Issue 1 May 2007 Page 7 Connect the grounding wire to the grounding system Leave sufficient slack in the grounding wire to allow it to be routed into the cabinet after the cabinet is mounted on t...

Page 8: ...cation may be verified at any time by contacting ADC s Technical Assistance Center ADC Telecommunications S PORE PTE LTD 100 Beach Road 18 01 Shaw Towers Singapore 189702 ADC Telecommunications INC PO...

Reviews: