X-TENSION 350 Median - Preparation for all Applications
Before installing an X-TENSION 350 Median, ensure that all materials required for an 11.43m
system are on site and have been identified. See parts identification sheet.
Ensure that the area where the X-TENSION 350 Median is to be installed is flat enough so that
the soil anchor will not protrude more than 100mm from ground level, when measured with a
straight line over a 1.5m cord. The maximum slope should not exceed 7%. Slopes above this
may cause the terminal to behave differently in a vehicle impact to what was tested. Minor site
grading may be required.
Soil Conditions
The X-TENSION 350 Median has been designed for installation in Median locations and in soil
that meets or exceeds the AASHTO “standard soil” specification. If rock is encountered during
post installation, refer to local road controlling authority specifications.
Tools Required
The same tools required to install standard highway guardrail will also install an X-TENSION
350 Median.
Specifically:
Sockets (commonly used in Guardrail), Drill, Wrenches, Large Crow Bar, String
line, Level, Augers, Tampers and Post Pounders commonly used in driving posts.
Before Starting
For all applications
, begin the installation from the downstream end of the terminal at the
point where it joins the standard guardrail (post 7).
The median application X-TENSION 350 Median connects directly to standard steel post , W-
beam highway guardrail.
Follow step-by-step instructions for the appropriate application.
Important note about posts and blockouts:
Median system:
Posts 1 & 2 are always crimped steel
Posts 3 – 6 are standard steel I beam posts
Blockouts are composite plastic