background image

 

ZoneScan II Field Installation Instructions 

10 | 

P a g e

 

J.

 

Connect 6-foot Lanyard to bottom 
carabiner of Transmission Unit (with 
extension if necessary) to the loop on the 
ZoneScan 820 Sensor. 

K.

 

Connect Communication Cable to 
ZoneScan 820 Sensor and the 
Transmission Unit (add another 
Communication Cable if required from 
Step I) 

L.

 

Orient the Lid / Antenna Assembly 
facing toward the sky (Aclara logo 
facing up) 

M.

 

Swipe the magnet once, wait for LEDs 
to light and swipe magnet a second time 
within 15 seconds to begin 
commissioning. The green light will 

come on and stay on for 15 seconds to 
confirm commissioning was successful. 

N.

 

Carry the fully assembled ZoneScan II 
Unit to the valve stack 

O.

 

Place the ZoneScan 820 Sensor into the 
valve stack first making sure it connects 
to valve nut and continue to lower the 
Unit into the valve stack until the Unit is 
in place with the Lid / Antenna 
Assembly in the place of the original 
metal lid.

 

IMPORTANT! 

The 7 ¼” Non-Metallic 

Valve Lid / Antenna Assembly is designed 
to accommodate RF transmissions. DO NOT 
paint or otherwise alter the Non-Metallic 
Valve Lid. 

Decommissioning 

The ZoneScan II System should be 
decommissioned prior to removal from the 
site or redeployment.  To decommission the 
Unit: 

1.

 

Remove the ZoneScan II unit from 
the from the valve stack and move to 
a safe location. 

2.

 

Replace the cast iron valve lid 

3.

 

Hold the magnet over the area shown 
below for a couple of seconds to 

Summary of Contents for ZoneScan II

Page 1: ...ZoneScan II Field Installation Instructions Y63158 TUM Revision A www Aclara com...

Page 2: ...rmware described in this document is furnished under a license and may be used or copied only in accordance with the terms of such license Disclaimer The information in this document is subject to cha...

Page 3: ...igital device pursuant to part 15 of the FCC Rules These limits are designed to provide reasonable protection against harmful interference in a residential installation This equipment generates uses a...

Page 4: ...nt structure s providing a separation distance of at least 20 cm from all persons during normal operation This device is not designed to operate in conjunction with any other antennas or transmitters...

Page 5: ...our offrir une protection raisonnable contre l interf rence nuisible dans une installation r sidentielle Cet quipement g n re utilise et peut mettre de l nergie de fr quences radio et s il n est pas i...

Page 6: ...n a aucun branchement externe pour tre utilis en association avec toute autre antenne ou tout transmetteur Aucune autre instruction d utilisation n est requise pour assurer la conformit aux r gles d...

Page 7: ...installations ZoneScan Technical Manual Y20284 TUM The technical manual provides information about acoustic leak detection and monitoring ZoneScan data Commissioning Document obtain document from Ralp...

Page 8: ...oneScan II Field Installation Instructions 8 P a g e Identification ZoneScan 820 Sensor Communication Cable 7 Non Metallic Valve Lid Antenna Assembly 6 foot Lanyard Transmission Unit Completed Assembl...

Page 9: ...ack the Valve Lid Antenna Assembly C Unpack ZoneScan II Transmission Unit and ZoneScan Sensor Communication Cable and 6 Lanyard D Connect the top lanyard away from the logo on MTU to stainless steel s...

Page 10: ...uccessful N Carry the fully assembled ZoneScan II Unit to the valve stack O Place the ZoneScan 820 Sensor into the valve stack first making sure it connects to valve nut and continue to lower the Unit...

Page 11: ...t yellow Gutermann cable from logger and MTU II Disconnect carabiner from 6 foot lanyard III Disconnect 6 foot lanyard from top of logger IV Disconnect carabiner from stainless steel sling under the l...

Reviews: