94MS41 Rev. C1 S/W Ver 2.06
1-3
•
Connect the main leads to the 4 position or 6 position terminal block and
connect the ground lead to the single ground terminal (see next page for
hook up).
•
Reinstall the lower side door.
•
Energize the main power circuit. You should hear the lamp head and
power supply cooling fans go into a cool-down cycle. Ensure that the
voltage select switch on the hinged control panel is switched to the lit
LED.
•
Install the lower front and rear black trim pieces over the forklift channels,
using a
5
/
32
" Allen wrench.
Electrical specifications and connections
Earth
Ground
L1
L2
L1 L2
L3
Figure A
380 / 415V~ 50Hz Connection
Wye: 3 Wires + N Ground
Terminal Block
N
380 / 415V~
OLITE
Power Supply
Blowers
Vacuum
Pumps
Electronics
Drives
Etc.
L3
N
Earth
Ground
L1
L2
L1 L2
L3
Figure B
208/240V~ 50Hz Connection
DELTA: 3 Wires + Ground
Terminal Block
N
208V~
OLITE
Power Supply #1
Blowers
Vacuum
Pumps
Electronics
Drives
Etc.
L3
208V~
OLITE
Power
Supply #1
AP 30CL - 6000 printer input
3 phase (Delta)
See Figure B
3 wires + ground
208/240V~ 60 Hz, 65 amp.
3 phase (Wye)
See Figure A
3 wires + n ground
380/415V~ 50 Hz, 34 amp.