Procedure
1. Contact the manufacturer to order the
foundation for your EVSE. Refer to
section
2. Dig the hole for the foundation.
Caution: Make sure that the
top surface of the
foundation is above the
ground level, to prevent
intrusion of water.
3. Guide the cable conduits into the
holes of the foundations:
•
Holes (A): CAN, interlock and DC
guard or AC auxiliary power and PE
cables
•
Holes (B): DC or AC power cables
4. Install the foundation in the hole.
5. Pull the cables through the cable conduits in the foundation. Apply the full cable
slack.
For the specification of the cable slack, refer to section
6. Fill the foundation with gravel or another substance to prevent rodents to enter
the cabinet.
4.4.3
Prepare a custom foundation for the power cabinet
Preliminary requirements
•
Custom foundation. Refer to section
Procedure
1. Make the custom foundation.
Caution: Make sure that the
top surface of the
foundation is above the
ground level, to prevent
intrusion of water.
2. Guide the cables into the holes (C1) to
(C7) of the foundations. For the
relation between the cables and the
.
3. Install the foundation in the hole.
4. Put the cables through the openings in
the foundation. Apply the full cable
slack.
For the cable slack, refer to section
5. Fill the foundation with gravel or another substance to prevent rodents to enter
the cabinet.
A
B
B
C2
C1
C5
C6
C7
C3
C4
Pre-installation
9AKK107992A6488-EN | 004
29
Summary of Contents for Terra HP Generation 3
Page 103: ...Technical data 9AKK107992A6488 EN 004 103 ...
Page 104: ......