4
Pre-installation
4.1
Pre-installation procedure (site planning)
Preliminary requirements
1.
All required permits to comply with the local rules, are granted.
Procedure
1. Do a check on the configuration of the EVSE. Refer to the order.
2. Refer to the specifications to prepare and order these items:
•
.
•
Cable specifications. Refer to section
3. Make sure that the cable slack for each cable is sufficient to guide the cables in
the cabinets. Refer to section
4. Prepare the site. Refer to section
.
5. Make sure that the floor space for the EVSE and the airflow around the EVSE is
correct. Refer to section
6. Prepare the underground installation:
a. Prepare the cable conduits. For the overview of the cable conduits, refer to
.
b. Prepare the foundations. Refer to section
7. If the local rules require the installation of extra items, plan the installation of
these items.
Examples:
•
External residual-current device. Refer to section
.
•
Options. Refer to section
.
4.2
Prepare the site
1. Make sure that the design of the site complies with these specifications:
•
The length of the charge cables is sufficient for connection to the charge
inlet of the EV. For the length and cable reach of the charge cables, refer to
•
The maximum distance between the power cabinets. Refer to section
.
•
The maximum distance between the power cabinet and the charge post.
Refer to section
.
2. Create a slope to drain the water away from the EVSE.
3. Create a parking space that allows the EV to have easy access to the EV charge
cable.
4. Apply road signs or markings to indicate that the parking space is intended for
EV charge sessions.
5. Install barriers or posts around the power cabinet and between the charge post
and the parking space.
6. Increase the height of the pavement and make sure that it is clearly visible, to
prevent damage of the EV.
Pre-installation
9AKK107992A6488-EN | 004
27
Summary of Contents for Terra HP Generation 3
Page 103: ...Technical data 9AKK107992A6488 EN 004 103 ...
Page 104: ......