5.3.3
Side-by-side 19” rack mounting
IP10323-1 v1
5.3.3.1
Overview
M11974-3 v3
IED case size 1/2 x 19” and RHGS cases can be mounted side-by-side up to a maximum size of 19”.
For side-by-side rack mounting, the side-by-side mounting kit together with the 19” rack panel
mounting kit must be used. The mounting kit has to be ordered separately.
Use only the screws included in the mounting kit when mounting the plates and the
angles on the IED. Screws with wrong dimension may damage the PCBs inside the
IED.
5.3.3.2
Mounting procedure for side-by-side rack mounting
M11955-2 v4
IEC17000121-1-en.vsdx
1
2
3
4
3
IEC17000121 V1 EN-US
Figure 5:
Side-by-side rack mounting details.
The required torque for the screws is 3.5 Nm.
PosNo
Description
Quantity
Type
1
Mounting plate
2
-
2, 3
Screw
16
M4x6
4
Mounting angle
2
-
5
Washer
16
M4x6
1MRK 514 030-UEN Rev. C
Section 5
Mounting
Switchgear control unit SAM600-IO
17
Installation manual
© 2017 - 2021 Hitachi Power Grids. All rights reserved