The commissioning manual contains instructions on how to commission the IED. The
manual can also be used by system engineers and maintenance personnel for assistance
during the testing phase. The manual provides procedures for the checking of external
circuitry and energizing the IED, parameter setting and configuration as well as
verifying settings by secondary injection. The manual describes the process of testing
an IED in a substation which is not in service. The chapters are organized in the
chronological order in which the IED should be commissioned. The relevant
procedures may be followed also during the service and maintenance activities.
The operation manual contains instructions on how to operate the IED once it has been
commissioned. The manual provides instructions for the monitoring, controlling and
setting of the IED. The manual also describes how to identify disturbances and how to
view calculated and measured power grid data to determine the cause of a fault.
The application manual contains application descriptions and setting guidelines sorted
per function. The manual can be used to find out when and for what purpose a typical
protection function can be used. The manual can also provide assistance for calculating
settings.
The technical manual contains operation principle descriptions, and lists function
blocks, logic diagrams, input and output signals, setting parameters and technical data,
sorted per function. The manual can be used as a technical reference during the
engineering phase, installation and commissioning phase, and during normal service.
The communication protocol manual describes the communication protocols supported
by the IED. The manual concentrates on the vendor-specific implementations.
The point list manual describes the outlook and properties of the data points specific to
the IED. The manual should be used in conjunction with the corresponding
communication protocol manual.
The cyber security deployment guideline describes the process for handling cyber
security when communicating with the IED. Certification, Authorization with role
based access control, and product engineering for cyber security related events are
described and sorted by function. The guideline can be used as a technical reference
during the engineering phase, installation and commissioning phase, and during normal
service.
1.3.2
Document revision history
GUID-C8027F8A-D3CB-41C1-B078-F9E59BB73A6C v4
Document revision/date
History
–/May 2017
First release
Section 1
1MRK 511 408-UUS A
Introduction
34
Phasor measurement unit RES670 2.2 ANSI
Technical manual
Summary of Contents for Relion RES670
Page 1: ...RELION 670 SERIES Phasor measurement unit RES670 Version 2 2 ANSI Technical manual ...
Page 2: ......
Page 276: ...270 ...
Page 306: ...300 ...
Page 360: ...354 ...
Page 406: ...400 ...
Page 614: ...608 ...
Page 732: ...726 ...
Page 748: ...742 ...
Page 884: ...878 ...
Page 932: ...926 ...
Page 933: ...927 ...