10.12.2
Liquid medium supervision SSIML
GUID-6426FDDA-B949-4FE7-BF42-B52014A9344B v4
Prepare the IED for verification of settings as outlined in section
Values of logical signals for SSIMG protection are available on the local HMI
under
Main menu/Tests/Function status/Monitoring/InsulationLiquid(71)/
SSIML(71):x
, where x = 1, 2,....4.
Check that the input logical signal
BLOCK
is logical zero and that on the local
HMI, the logical signals
LVLALM
,
LVLLO
,
TEMPALM
,
TEMPLO
,
ALARM
and
LOCKOUT
are logical zero.
10.12.2.1
Testing the liquid medium supervision for level alarm and level
lockout conditions
GUID-C1F1E6CA-9512-4358-A4E7-84CC3698D156 v3
1.
Connect the binary inputs to consider liquid level to initiate the alarms.
2.
Consider the analogue level input
SENLEVEL
and set
SENLEVEL
to a value
lower than
LevelAlmLimit
or activate binary input signal
SENLVLALM
, check
that outputs
LVLALM
and
ALARM
are activated after a set time delay of
tLevelAlarm
.
3.
Liquid level lockout input
SENLVLLO
can be used to set
LVLLO
.
4.
Also, reduce the liquid level input below
LevelLOLimit
or activate the binary
input signal
SENLVLLO
, check that
LVLLO
signal after a set time delay of
tLevelLockOut
.
5.
Activate
BLOCK
binary input and check that the outputs
LVLALM
,
LVLLO
,
ALARM
and
LOCKOUT
disappears.
6.
Reset the
BLOCK
binary input.
7.
Make sure that level lockout condition exists and then activate the reset lock
out input
RESETLO
and check that the outputs
PRESLO
and
LOCKOUT
reset.
10.12.2.2
Testing the liquid medium supervision for temperature alarm and
temperature lock out conditions
GUID-189AF20B-D0E3-453D-A787-68F25D0903D3 v1
1.
Consider the analogue temperature input
SENTEMP
and set
SENTEMP
to a
value higher than
TempAlarmLimit
, check that outputs
TEMPALM
and
ALARM
are activated after a set time delay of
tTempAlarm
.
2.
Temperature lockout input
SETTLO
can be used to set
TEMPLO
signal.
3.
Also, increase further the temperature input above
TempLOLimit
, check that
the outputs
TEMPLO
and
LOCKOUT
appears after a set time delay of
tTempLockOut
.
1MRK 506 377-UEN C
Section 10
Testing functionality by secondary injection
Railway application RER670 2.2 IEC
165
Commissioning manual
Summary of Contents for RELION RER670
Page 1: ...RELION 670 SERIES Railway application RER670 Version 2 2 IEC Commissioning manual...
Page 2: ......
Page 26: ...20...
Page 54: ...48...
Page 58: ...52...
Page 62: ...56...
Page 80: ...74...
Page 188: ...182...
Page 194: ...188...
Page 204: ...198...
Page 214: ...208...
Page 215: ...209...